Building Permit Fees People Often Miss

The building permit fee is rarely the whole bill. Here is what else turns up in the 262 official fee schedules on this site, how often, and where.

The short answer

Most schedules add something to the base permit fee: plan review, state surcharges or technology fees. Many list fees that only apply to some projects, and the largest costs for a new home, such as impact fees and utility connections, are often charged outside the building permit by a different department or district. Each city page on this site separates what is in the total from what may also apply.

Add-ons already in the total

These are charged with the building permit itself, so our calculator totals include them. They are easy to miss when you only read the main fee table.

Plan review is the biggest add-on of all and has its own guide: plan review fee vs permit fee.

Fees that apply only sometimes

Schedules often list fees that depend on the project or the site. We show these on each city page as "may also apply" and leave them out of the total, because a wrong guess either way would mislead.

Fees charged outside the building permit

For new homes and additions these can be larger than the permit itself. They are usually set by another department, a utility or a school district, so the building fee schedule may only mention them.

Trade permits for electrical, plumbing and mechanical work are separate in most places and are often pulled by the licensed contractor doing that work.

Fees that come up later

These depend on how the project goes, not on its size:

  • Re-inspection fees: listed in 180 of 262 schedules (69%). Printed as, for example, "Reinspection".
  • After-hours and expedited inspections: listed in 107 of 262 schedules (41%). Printed as, for example, "After-hours inspection".
  • Permit extensions and reinstatement: listed in 84 of 262 schedules (32%). Printed as, for example, "Permit extension".
  • Work started without a permit: listed in 84 of 262 schedules (32%). Printed as, for example, "Investigation fee".

Failed inspections are the most common of these: a re-inspection fee is charged each time an inspector has to come back.

Before you budget

  1. Find your place in the calculator and note the "may also apply" list.
  2. For a new home or addition, ask the permit office which impact, utility and school fees apply, and who collects them.
  3. Check whether your contractor's price includes the trade permits.
  4. Read the gaps list on the city page: it says what the official schedule did not let us price.

Figures computed November 5, 2026 from the official fee schedules on this site. Fees are estimates based on the official schedules; confirm with the permit office before applying.