BuildingPermitCost

Building Permit Fees in Anchorage, AK (2026)

Anchorage prices building permits with 0.9% of project value, with a $450.00 minimum, then charges plan review at $5.00 per $1,000 of project value (minimum $75.00). Enter your project to see the exact math.

  • Official city schedule
  • Effective not stated
  • Verified Nov 4, 2026
Minimum fee
$450.00
Plan review
Separate
$75k addition
$1,201

Permit fee calculator

Anchorage schedule
Project type
Estimated permit fees $1,201.25
  1. 1. Building permit fee
    0.9% of $75,000.00
    $675.00
  2. 2. Plan review fee
    $75,000.00 ÷ 1,000 × $5.00
    $375.00
  3. 3. Land use plan review
    15% of $675.00
    $101.25
  4. 4. Digital maintenance fee (residential construction permit)
    fixed
    $50.00

May also apply (not in the total)

  • Expedited plan review (initial permit)
    When: optional expedited review
    $405.00

Fees are estimates based on the official schedule linked below. Confirm with the permit office before applying. Separate electrical, plumbing, mechanical, fire, impact, utility and school fees are usually not included unless they are listed. BuildingPermitCost is not a government permit office, and this is not legal advice.

What common projects cost

Kitchen or bath remodel
$25,000 value, remodel 300 sq ft
$700.00
$450.00 building permit + $125.00 plan review + $75.00 land use plan review + $50.00 digital maintenance fee (residential construction permit)
Room addition
$75,000 value, addition 400 sq ft
$1,201.25
$675.00 building permit + $375.00 plan review + $101.25 land use plan review + $50.00 digital maintenance fee (residential construction permit)
New single-family home
$350,000 value, new single-family 2,400 sq ft
$5,422.50
$3,150.00 building permit + $1,750.00 plan review + $472.50 land use plan review + $50.00 digital maintenance fee (residential construction permit)

How Anchorage calculates your permit fee

The city charges a building permit fee using 0.9% of project value, with a $450.00 minimum. Plan review is a separate charge: $5.00 per $1,000 of project value (minimum $75.00). Electrical, plumbing and mechanical work gets its own permits.

The fee table

Residential construction, all others (new, additions, alterations, repairs)

0.9% of project value, with a $450.00 minimum.

Commercial construction

Project valueFee
$1 – $1,000,000$12.00 per $1,000
$1,000,001 – $5,000,000$12,000.00 for the first $1,000,000 + $8.00 per additional $1,000
Over $5,000,000$44,000.00 for the first $5,000,000 + $6.00 per additional $1,000

Added to every matching permit

  • Fire Department plan review (commercial): $1.10 per $1,000 of project value, with a $75.00 minimum (Commercial)

Surcharges

  • Land use plan review: 15% of the permit fee, minimum $75.00
  • Digital maintenance fee (residential construction permit): $50.00
  • Digital maintenance fee (commercial construction permit): $75.00

What counts as project value

Not stated in the schedule. Building Safety and plan review fees are multiples of '(Valuation)'; the fee tables do not say how valuation is determined.

Worked example: a $350,000 new home

  1. Building permit fee: 0.9% of $350,000.00 = $3,150.00
  2. Plan review fee: $350,000.00 ÷ 1,000 × $5.00 = $1,750.00
  3. Land use plan review: 15% of $3,150.00 = $472.50
  4. Digital maintenance fee (residential construction permit): fixed = $50.00
  5. Total before trade permits: $5,422.50.

Fees people miss

May also apply (not in the totals above)

  • Expedited plan review (initial permit): when optional expedited review; $270.00 on the standard projects.
FeeAmount
Inspection beyond allotted quantity / first re-inspectionWhen: extra inspections $175.00 per hour
Second and subsequent re-inspectionsWhen: repeat re-inspections $265.00 per hour
Express plan reviewWhen: optional express review $280.00 per hour per discipline
Code research, change orders, alternate materials, misc. reviewWhen: revisions or special review $175.00 per discipline per hour
Change of use (no alteration)When: change of use only $350.00 each
Permit reactivationWhen: reactivation of expired permit $175.00 each

Trade permits are separate. Electrical: Stand-alone trade permit (no structural work) $175 incl. 2 inspections; retrofit permits (one 20 A circuit, up to six receptacles/fixtures) $175. Plumbing: Stand-alone trade permit $175 incl. 2 inspections; like-for-like replacements $175. Mechanical: Stand-alone trade permit $175 incl. 2 inspections.

How to apply

  1. Gather your plans and your project's total value.
  2. Submit to Municipality of Anchorage Development Services, Building Safety.
  3. Pay the permit and plan review fees when invoiced.

How Anchorage compares

A $25,000 remodel costs $700.00 in Anchorage: 84% above the national median of $380.00.

A $75,000 addition costs $1,201.25 in Anchorage: 46% above the national median of $820.58.

A $350,000 new home costs $5,422.50 in Anchorage: 86% above the national median of $2,918.63.

Same standard projects everywhere, including plan review and required surcharges. All Alaska places · Compare side by side

Anchorage permit fee FAQ

How much is a building permit in Anchorage, AK?

A $25,000 remodel: $700.00. A $75,000 addition: $1,201.25. A $350,000 new single-family: $5,422.50. These include every fee the schedule applies to that project; trade permits are separate.

Is plan review included in the Anchorage permit fee?

No. Plan review is charged separately at $5.00 per $1,000 of project value (minimum $75.00).

How does Anchorage determine project value?

Not stated in the schedule. Building Safety and plan review fees are multiples of '(Valuation)'; the fee tables do not say how valuation is determined.

Are electrical, plumbing and mechanical permits included?

No. They are separate permits. Electrical: Stand-alone trade permit (no structural work) $175 incl. 2 inspections; retrofit permits (one 20 A circuit, up to six receptacles/fixtures) $175. Plumbing: Stand-alone trade permit $175 incl. 2 inspections; like-for-like replacements $175. Mechanical: Stand-alone trade permit $175 incl. 2 inspections.

When did these Anchorage fees take effect?

The schedule does not state an effective date. We last checked it against the official source on Nov 4, 2026.