How Greenwood calculates your permit fee
The city charges a building permit fee using a fee table based on floor area.
The fee table
Single-family dwelling
| Floor area | Fee |
|---|---|
| Over 0 sq ft | $400.00 + $0.05 per additional sq ft or fraction |
Residential (1-2 family) addition
| Floor area | Fee |
|---|---|
| Over 0 sq ft | $225.00 + $0.05 per additional sq ft or fraction |
Residential remodel (structural component)
A flat $75.00.
Commercial/industrial new building (excluding per-acre charge)
| Floor area | Fee |
|---|---|
| Over 0 sq ft | $750.00 + $0.05 per additional sq ft or fraction |
Added to every matching permit
- Park impact fee (single-family home): a flat $2,748.00 (Residential · new construction)
What counts as project value
Not used. Residential and commercial building permit fees are a flat amount plus $0.05 per square foot; project value is not used. The source does not define which floor area the per-square-foot charge measures.
Worked example: a $350,000 new home
- Building permit fee: $400.00 for the first 0 sq ft + $0.05 × 2,400 per sq ft over = $520.00
- Park impact fee (single-family home): flat fee = $2,748.00
- Total before trade permits: $3,268.00.
Fees people miss
May also apply (not in the totals above)
- Sewer connection permit fee (3/4 or 5/8 inch meter): when the home connects to city sewer with a new water meter; $835.00 on the standard projects.
- Sewer availability fee (3/4 or 5/8 inch meter): when new or increased-size water meter connection; $2,073.00 on the standard projects.
| Fee | Amount |
|---|---|
| Permit reinspection feeWhen: reinspection | $75.00 each |
| Temporary Certificate of OccupancyWhen: temporary CO requested | $100.00 each |
| Starting work without required permit(s)When: work started without permit | 2.00 times permit base fee |
| Permit renewal/extension (1 year)When: renewal | 1/2 original permit base fee |
| Expedited permit reviewWhen: expedited review requested | $250.00 each |
| Certificate of occupancy | $0.00 each |
| Erosion and sediment control permitWhen: land disturbance over 10,000 sf but under 1 acre | $100.00 each |
| Stormwater management permitWhen: land disturbance of 1 acre or more | $450.00 each |
How to apply
- Gather your plans and your project's total value.
- Submit to Building Commissioner, Community Development Services.
- Pay the permit and plan review fees when invoiced.
- Questions: 317.881.8698 · 300 S. Madison Ave., Greenwood, IN 46142