How Hamilton County calculates your permit fee
The county charges a building permit fee using $0.10 per square foot, plus a $200.00 application fee. Electrical, plumbing and mechanical work gets its own permits.
The fee table
Single family dwelling
$0.10 per square foot, plus a $200.00 application fee.
Dwelling addition / attached garage
$0.10 per square foot, plus a $175.00 application fee.
Dwelling remodel
$0.10 per square foot, plus a $150.00 application fee.
Commercial primary structure
$0.15 per square foot, plus a $350.00 application fee.
Commercial addition
$0.15 per square foot, plus a $250.00 application fee.
Commercial remodel
$0.15 per square foot, plus a $200.00 application fee.
Added to every matching permit
- Certificate of Occupancy (residential): a flat $95.00 (Residential · new construction, additions, remodels and alterations)
- Certificate of Occupancy (commercial): a flat $125.00 (Commercial · new construction, additions, remodels and alterations)
What counts as project value
Floor area (square feet). Fees are a base amount plus a rate per square foot; no construction valuation is used. Dwellings count 'total sq. ft. (including covered porches, garages, basements, attics with access and stairways)'.
Worked example: a $350,000 new home
- Building permit fee: 2,400 sq ft × $0.10 = $240.00
- Application fee: fixed = $200.00
- Certificate of Occupancy (residential): flat fee = $95.00
- Total before trade permits: $535.00.
Fees people miss
May also apply (not in the totals above)
- Inspections (residential): when the Plan Commission charges its listed inspection fee (per inspection or per permit is not stated); $100.00 on the standard projects.
- Construction before permit (penalty multiple): when construction or change of use started before obtaining the permit; $15.00 on the standard projects.
| Fee | Amount |
|---|---|
| Missed inspection (per project)When: missed inspection | $150.00 each |
| Permit extensionWhen: permit extension requested | $40.00 each |
| Amended application after filingWhen: application amended after docket number assigned | $50.00 each |
| Occupying before Certificate of OccupancyWhen: occupancy before C/O issued | $1,200.00 each |
Trade permits are separate. Electrical: Electrical permits: residential $90, other $175.
How to apply
- Gather your plans and your project's total value and floor area.
- Submit to Hamilton County Plan Commission.
- Pay the permit and plan review fees when invoiced.
- Questions: One Hamilton County Square, Suite 306, Noblesville, IN 46060