How Carmel calculates your permit fee
The city charges a building permit fee using a fee table based on floor area. Electrical, plumbing and mechanical work gets its own permits.
The fee table
Class II Structure - New (ILP)
| Floor area | Fee |
|---|---|
| Over 0 sq ft | $650.00 + $0.25 per additional sq ft or fraction |
Class II Structure - Addition
| Floor area | Fee |
|---|---|
| Over 0 sq ft | $350.00 + $0.25 per additional sq ft or fraction |
Class II Structure - Remodel
| Floor area | Fee |
|---|---|
| Over 0 sq ft | $250.00 + $0.25 per additional sq ft or fraction |
Class I Structure - New
| Floor area | Fee |
|---|---|
| Over 0 sq ft | $1,250.00 + $0.25 per additional sq ft or fraction |
Class I Structure - Addition
| Floor area | Fee |
|---|---|
| Over 0 sq ft | $950.00 + $0.25 per additional sq ft or fraction |
Class I Structure - Remodel
| Floor area | Fee |
|---|---|
| Over 0 sq ft | $750.00 + $0.25 per additional sq ft or fraction |
Added to every matching permit
- Certificate of Occupancy (Class II): a flat $100.00 (Residential · new construction)
- Certificate of Occupancy (Class I): a flat $250.00 (Commercial · new construction)
What counts as project value
Floor area (square feet). Improvement Location Permit fees are a base fee plus a rate per gross square foot by structure class and work type; construction valuation is not used in the 2026 schedule.
Worked example: a $350,000 new home
- Building permit fee: $650.00 for the first 0 sq ft + $0.25 × 2,400 per sq ft over = $1,250.00
- Certificate of Occupancy (Class II): flat fee = $100.00
- Total before trade permits: $1,350.00.
Fees people miss
| Fee | Amount |
|---|---|
| Construction inspection, Class II structure | $100.00 each inspection |
| Reinspection, Class IIWhen: failed inspection | $150.00 each |
| Timed/same-day/weekend inspectionWhen: timed, same-day or weekend inspection requested | 2x regular fee |
| Electrical permit, Class II structureWhen: meter base or panel upgrade, solar, generator or vehicle charging installation | $100.00 each |
| Re-review fee, Class IIWhen: plans re-reviewed | $250.00 each |
| Permit late fee, Class II new or additionWhen: permit obtained late (work started first) | $1,000.00 each |
| Builder Application (annual fee)When: builder registration | $150.00 per year |
| Tree Preservation - preconstructionWhen: tree preservation inspection required | $500.00 each |
Trade permits are separate. Electrical: Electrical permits: Class I structure $200, Class II structure $100 (meter base/panel upgrade, solar, generator, vehicle charging).
How to apply
- Gather your plans and your project's total value and floor area.
- Submit to Department of Community Services, Division of Building Safety.
- Pay the permit and plan review fees when invoiced.