How Garden Grove calculates your permit fee
The city charges a building permit fee using a fee table based on project value, plus a $64.00 application fee, with a $145.00 minimum. Plan review is a separate charge: 65% of the permit fee (minimum $60.00). Electrical, plumbing and mechanical work gets its own permits.
The fee table
| Project value | Fee |
|---|---|
| $1 – $2,000 | $145.00 |
| $2,001 – $25,000 | $144.75 for the first $2,000 + $18.88 per additional $1,000 or fraction |
| $25,001 – $50,000 | $579.00 for the first $25,000 + $23.16 per additional $1,000 or fraction |
| $50,001 – $100,000 | $1,158.00 for the first $50,000 + $7.72 per additional $1,000 or fraction |
| $100,001 – $500,000 | $1,544.00 for the first $100,000 + $10.62 per additional $1,000 or fraction |
| $500,001 – $1,000,000 | $5,790.00 for the first $500,000 + $4.63 per additional $1,000 or fraction |
| Over $1,000,000 | $8,106.00 for the first $1,000,000 + $4.40 per additional $1,000 or fraction |
Plus an application fee of $64.00.
Added to every matching permit
- General Plan and Cultural Arts Fee: a fee table based on project value (All projects)
Surcharges
- Building Permit Software Fee: $10.00
- Building Permit Document Retention Fee: $5.00
- One-Stop Construction Services Center Surcharge: 2% of the permit fee
- Strong Motion Instrumentation Program (residential up to 3 stories): $0.13 per $1,000 of value
- Strong Motion Instrumentation Program (all other): $0.28 per $1,000 of value
- State Building Standards Administrative Special Revolving Fund Fee (SB 1473): $1.00 per $25,000 of value
What counts as project value
Not stated in the schedule. The building permit fee table is by 'Total Valuation'. The user fee schedule does not say how valuation is determined for the building permit table (the General Plan and Cultural Arts Fee refers to 'valuation as determined by the Building Official'). A separate valuation table PDF may exist on the Building & Safety pages (not read).
Worked example: a $350,000 new home
- Building permit fee: $1,544.00 for the first $100,000.00 + $10.62 × 250 per $1,000.00 over = $4,199.00
- Application fee: fixed = $64.00
- Plan review fee: 65% of $4,199.00 = $2,729.35
- General Plan and Cultural Arts Fee: $2.00 for the first $0.00 + $1.75 × 350 per $1,000.00 over = $614.50
- Building Permit Software Fee: fixed = $10.00
- Building Permit Document Retention Fee: fixed = $5.00
- One-Stop Construction Services Center Surcharge: 2% of $4,199.00 = $83.98
- Strong Motion Instrumentation Program (residential up to 3 stories): $350,000.00 ÷ 1,000 × $0.13 = $45.50
- State Building Standards Administrative Special Revolving Fund Fee (SB 1473): $1.00 × 14 per $25,000.00 = $14.00
- Total before trade permits: $7,765.33.
Fees people miss
May also apply (not in the totals above)
- Plan review increase - state green building standards: when project subject to state green building standards (typical new house); $37.63 on the standard projects.
- Plan review increase - state energy conservation standards: when project subject to state energy conservation standards (typical new house); $37.63 on the standard projects.
- Plan review increase - state disabled access standards: when building subject to state disabled access standards; $37.63 on the standard projects.
- Plan review increase - flood hazard overlay zone: when project located in a flood hazard overlay zone; $7.53 on the standard projects.
- Planning plan check - single family residential (up to three houses): when Planning Division plan check; schedule does not say it applies to every building permit; $50.00 on the standard projects.
- Engineering plan check for private projects - single family residential (up to three houses): when Engineering plan check for private projects; schedule does not say it applies to every building permit; $55.00 on the standard projects.
| Fee | Amount |
|---|---|
| Issuance Fee for Combination PermitWhen: combination permit instead of single permit | $97.00 each |
| Supplemental Permit Issuance FeeWhen: supplemental permit | $32.00 each |
| Plan Retention FeeWhen: per plan sheet retained | $4.00 per sheet |
| Planning Document Retention FeeWhen: planning documents | $35.00 each |
| Reinspection feeWhen: reinspection | $193.00 each |
| Supplemental Plan ReviewWhen: supplemental review | $193.00 per hour (one hour minimum) |
| Overtime Inspection FeeWhen: inspection outside business hours | $232.00 per hour (two hour minimum) |
Trade permits are separate. Electrical: Electrical plan review 85% of building permit fee ($97 min.); itemized electrical fees not extracted. Mechanical: Mechanical plan check 85% of building permit fee ($97 min.); itemized fees not extracted. Plumbing: Plumbing plan check 85% of building permit fee ($97 min.); building sewer first 100 ft $37, each additional 100 ft $12; other items not extracted.
How to apply
- Gather your plans and your project's total value.
- Submit to Community and Economic Development - Building & Safety.
- Pay the permit and plan review fees when invoiced.
- Questions: 714-741-5000 · 11222 Acacia Parkway, Garden Grove, CA 92840