How Volusia County calculates your permit fee
The county charges a building permit fee using a fee table based on project value, with a $60.34 minimum. Plan review is a separate charge: its own fee table. Electrical, plumbing and mechanical work gets its own permits.
The fee table
| Project value | Fee |
|---|---|
| $1 – $2,000 | $60.34 |
| $2,001 – $40,000 | $60.34 for the first $2,000 + $8.05 per additional $1,000 |
| $40,001 – $100,000 | $366.10 for the first $40,000 + $6.00 per additional $1,000 |
| $100,001 – $500,000 | $726.15 for the first $100,000 + $3.98 per additional $1,000 |
| Over $500,000 | $2,319.10 for the first $500,000 + $1.96 per additional $1,000 |
What counts as project value
ICC Building Valuation Data table. "Value of construction for permits will be determined by the most recent publishing of the International Code Council estimates per square foot, including the regional modifier, of all areas under roof according to the type of construction and use."
Worked example: a $350,000 new home
- Building permit fee: $726.15 for the first $100,000.00 + $3.98 × 250 per $1,000.00 over = $1,721.15
- Plan review fee: $130.75 for the first $150,000.00 + $30.13 × 4 per $50,000.00 over = $251.27
- Total before trade permits: $1,972.42.
Fees people miss
May also apply (not in the totals above)
- Work without a permit: when work started without a required permit (double permit fee); $245.49 on the standard projects.
| Fee | Amount |
|---|---|
| Application fee, one and two family residencesWhen: credited toward the permit fee; only a net cost if the permit is not obtained | $201.29 each |
| Application fee, commercial buildingWhen: credited toward the permit fee; only a net cost if the permit is not obtained | $402.31 each |
| Application fee, all other miscellaneous applicationsWhen: credited toward the permit fee; only a net cost if the permit is not obtained | $60.34 each |
| Reinspection feeWhen: failed or extra inspection | $62.14 each |
| Certificate of Occupancy | $6.00 each |
| Pre-inspectionWhen: pre-inspection requested | $58.58 each |
| House moving feeWhen: moving a house | $201.29 each |
| Permit reinstatement, extension, and closeout feeWhen: reinstating, extending or closing out a permit | $25.00 each |
| Stormwater utility fee (prorated, new construction)When: new buildings in unincorporated areas, before Certificate of Occupancy | prorated by month |
| Residential solid waste fee (prorated, new homes)When: new residences in unincorporated areas | prorated by month |
| Impact feesWhen: new construction, expansion or change of use |
Trade permits are separate. Electrical: Minimum $60.34; new/increased service $0.78 per ampere increase (single phase); alterations $10.04 per circuit for first ten, $1.96 each additional. Plumbing: Minimum $60.34 plus $3.98 per fixture/appliance connected. Mechanical: Valuation table: $60.34 up to $1,000; $60.34 + $8.05 per additional thousand to $25,000; $253.45 + $5.16 per additional thousand above $25,000.
How to apply
- Gather your plans and your project's total value.
- Submit to Volusia County Building and Code Administration through Connect Live.
- Pay the permit and plan review fees when invoiced.
- Questions: Permit Center, 123 W. Indiana Ave., Room 203, DeLand, FL