Building Permit Fees in Melbourne, FL (2026)

Melbourne prices building permits with a fee table based on project value, then charges plan review at 50% of the permit fee. Enter your project to see the exact math.

  • Official city schedule
  • Effective Aug 7, 2026
  • Verified Nov 5, 2026
Minimum fee
—
Plan review
50%
$75k addition
$821

Permit fee calculator

Melbourne schedule, eff. Aug 7, 2026
Project type
Estimated permit fees $820.58
  1. 1. Building permit fee
    $383.50 for the first $50,000.00 + $5.50 × 25 per $1,000.00 over
    $521.00
  2. 2. Plan review fee
    50% of $521.00
    $260.50
  3. 3. Technology fee
    5% of $781.50
    $39.08

May also apply (not in the total)

  • Community Development Department permit review
    When: the permit is reviewed by the Community Development Department
    $25.00
  • Engineering Department permit review
    When: the permit is reviewed by the Engineering Department
    $25.00

Fees are estimates based on the official schedule linked below. Confirm with the permit office before applying. Separate electrical, plumbing, mechanical, fire, impact, utility and school fees are usually not included unless they are listed. BuildingPermitCost is not a government permit office, and this is not legal advice.

What common projects cost

Kitchen or bath remodel
$25,000 value, remodel 300 sq ft
$348.08
$221.00 building permit + $110.50 plan review + $16.58 technology
Room addition
$75,000 value, addition 400 sq ft
$820.58
$521.00 building permit + $260.50 plan review + $39.08 technology
New single-family home
$350,000 value, new single-family 2,400 sq ft
$2,800.35
$1,778.00 building permit + $889.00 plan review + $133.35 technology

How Melbourne calculates your permit fee

The city charges a building permit fee using a fee table based on project value. Plan review is a separate charge: 50% of the permit fee.

The fee table

Project valueFee
$1 – $1,000$65.00
$1,001 – $50,000$65.00 for the first $1,000 + $6.50 per additional $1,000 or fraction
$50,001 – $100,000$383.50 for the first $50,000 + $5.50 per additional $1,000 or fraction
$100,001 – $500,000$653.00 for the first $100,000 + $4.50 per additional $1,000 or fraction
Over $500,000$2,448.50 for the first $500,000 + $3.50 per additional $1,000 or fraction

Surcharges

  • Life Safety review: 25% of the permit fee
  • Technology fee: 5% of the fee total

What counts as project value

Higher of your bid or the valuation table. 'The cost of new construction shall be calculated using the most current edition ICC (International Code Council) building valuation data or contracted price, whichever is greater.'

Worked example: a $350,000 new home

  1. Building permit fee: $653.00 for the first $100,000.00 + $4.50 × 250 per $1,000.00 over = $1,778.00
  2. Plan review fee: 50% of $1,778.00 = $889.00
  3. Technology fee: 5% of $2,667.00 = $133.35
  4. Total before trade permits: $2,800.35.

Fees people miss

May also apply (not in the totals above)

  • Community Development Department permit review: when the permit is reviewed by the Community Development Department; $25.00 on the standard projects.
  • Engineering Department permit review: when the permit is reviewed by the Engineering Department; $25.00 on the standard projects.
FeeAmount
Permits with multiple tradesWhen: permit includes multiple trades $35.00 per trade review
Administrative permitWhen: administrative permit $125.00 each
Inspection fee for permits not based on ICC valuation tablesWhen: permit not based on valuation table
Review and re-stamp replacement copies of approved plansWhen: replacement plans $65.00 each
Re-inspection, firstWhen: failed inspection $38.00 each
Partial inspectionWhen: partial inspection $38.00 each
Additional plan check after two reviewsWhen: plans not approved after two reviews
Review revised plans after permit issuedWhen: revisions after issuance $35.00 per trade
Work without permitWhen: work started before permit
Failure to schedule final inspection within 180 daysWhen: final not scheduled in 180 days $125.00 each
Permit extensionWhen: extension granted $35.00 each
Beneficial use up to 30 daysWhen: beneficial use requested $125.00 each
1 more fees
  • Exemption request: $62.50 each

How to apply

  1. Gather your plans and your project's total value.
  2. Submit to the city building department.
  3. Pay the permit and plan review fees when invoiced.

How Melbourne compares

A $25,000 remodel costs $348.08 in Melbourne: 8% below the national median of $380.00, and the 10th lowest of 19 places we cover in Florida (state median $348.08).

A $75,000 addition costs $820.58 in Melbourne: about the same as the national median of $820.58, and the 7th highest of 17 places we cover in Florida (state median $500.09).

A $350,000 new home costs $2,800.35 in Melbourne: about the same as the national median of $2,918.63, and the 8th highest of 19 places we cover in Florida (state median $2,400.00).

Same standard projects everywhere, including plan review and required surcharges. All Florida places · Compare side by side

Melbourne permit fee FAQ

How much is a building permit in Melbourne, FL?

A $25,000 remodel: $348.08. A $75,000 addition: $820.58. A $350,000 new single-family: $2,800.35. These include every fee the schedule applies to that project; trade permits are separate.

Is plan review included in the Melbourne permit fee?

No. Plan review is charged separately at 50% of the permit fee.

How does Melbourne determine project value?

Higher of your bid or the valuation table. 'The cost of new construction shall be calculated using the most current edition ICC (International Code Council) building valuation data or contracted price, whichever is greater.'

When did these Melbourne fees take effect?

The schedule is effective Aug 7, 2026 (“Building Permit Fees, Effective August 7, 2026”). We last checked it against the official source on Nov 5, 2026.