How Arapahoe County calculates your permit fee
The county charges a building permit fee using a fee table based on project value, with a $94.73 minimum. Plan review is a separate charge: 65% of the permit fee.
The fee table
| Project value | Fee |
|---|---|
| $1 – $100,000 | $94.73 to $1,490.62, read from the table (101 steps) |
| $100,001 – $500,000 | $1,490.62 for the first $100,000 + $11.20 per additional $1,000 or fraction |
| $500,001 – $1,000,000 | $5,970.62 for the first $500,000 + $9.50 per additional $1,000 or fraction |
| Over $1,000,000 | $10,720.62 for the first $1,000,000 + $6.30 per additional $1,000 or fraction |
Show the full table (104 rows)
| $1 – $1,800 | $94.73 |
| $1,801 – $1,900 | $99.30 |
| $1,901 – $2,000 | $103.87 |
| $2,001 – $3,000 | $124.87 |
| $3,001 – $4,000 | $145.87 |
| $4,001 – $5,000 | $166.87 |
| $5,001 – $6,000 | $187.87 |
| $6,001 – $7,000 | $208.87 |
| $7,001 – $8,000 | $229.87 |
| $8,001 – $9,000 | $250.87 |
| $9,001 – $10,000 | $271.87 |
| $10,001 – $11,000 | $292.87 |
| $11,001 – $12,000 | $313.87 |
| $12,001 – $13,000 | $334.87 |
| $13,001 – $14,000 | $355.87 |
| $14,001 – $15,000 | $376.87 |
| $15,001 – $16,000 | $397.87 |
| $16,001 – $17,000 | $418.87 |
| $17,001 – $18,000 | $439.87 |
| $18,001 – $19,000 | $460.87 |
| $19,001 – $20,000 | $481.87 |
| $20,001 – $21,000 | $502.87 |
| $21,001 – $22,000 | $523.87 |
| $22,001 – $23,000 | $544.87 |
| $23,001 – $24,000 | $565.87 |
| $24,001 – $25,000 | $586.87 |
| $25,001 – $26,000 | $602.02 |
| $26,001 – $27,000 | $617.17 |
| $27,001 – $28,000 | $632.32 |
| $28,001 – $29,000 | $647.47 |
| $29,001 – $30,000 | $662.62 |
| $30,001 – $31,000 | $677.77 |
| $31,001 – $32,000 | $692.92 |
| $32,001 – $33,000 | $708.07 |
| $33,001 – $34,000 | $723.22 |
| $34,001 – $35,000 | $738.37 |
| $35,001 – $36,000 | $753.52 |
| $36,001 – $37,000 | $768.67 |
| $37,001 – $38,000 | $783.82 |
| $38,001 – $39,000 | $798.97 |
| $39,001 – $40,000 | $814.12 |
| $40,001 – $41,000 | $829.27 |
| $41,001 – $42,000 | $844.42 |
| $42,001 – $43,000 | $859.57 |
| $43,001 – $44,000 | $874.72 |
| $44,001 – $45,000 | $889.87 |
| $45,001 – $46,000 | $905.02 |
| $46,001 – $47,000 | $920.17 |
| $47,001 – $48,000 | $935.32 |
| $48,001 – $49,000 | $950.47 |
| $49,001 – $50,000 | $965.62 |
| $50,001 – $51,000 | $976.12 |
| $51,001 – $52,000 | $986.62 |
| $52,001 – $53,000 | $997.12 |
| $53,001 – $54,000 | $1,007.62 |
| $54,001 – $55,000 | $1,018.12 |
| $55,001 – $56,000 | $1,028.62 |
| $56,001 – $57,000 | $1,039.12 |
| $57,001 – $58,000 | $1,049.62 |
| $58,001 – $59,000 | $1,060.12 |
| $59,001 – $60,000 | $1,070.62 |
| $60,001 – $61,000 | $1,081.12 |
| $61,001 – $62,000 | $1,091.62 |
| $62,001 – $63,000 | $1,102.12 |
| $63,001 – $64,000 | $1,112.62 |
| $64,001 – $65,000 | $1,123.12 |
| $65,001 – $66,000 | $1,133.62 |
| $66,001 – $67,000 | $1,144.12 |
| $67,001 – $68,000 | $1,154.62 |
| $68,001 – $69,000 | $1,165.12 |
| $69,001 – $70,000 | $1,175.62 |
| $70,001 – $71,000 | $1,186.12 |
| $71,001 – $72,000 | $1,196.62 |
| $72,001 – $73,000 | $1,207.12 |
| $73,001 – $74,000 | $1,217.62 |
| $74,001 – $75,000 | $1,228.12 |
| $75,001 – $76,000 | $1,238.62 |
| $76,001 – $77,000 | $1,249.12 |
| $77,001 – $78,000 | $1,259.62 |
| $78,001 – $79,000 | $1,270.12 |
| $79,001 – $80,000 | $1,280.62 |
| $80,001 – $81,000 | $1,291.12 |
| $81,001 – $82,000 | $1,301.62 |
| $82,001 – $83,000 | $1,312.12 |
| $83,001 – $84,000 | $1,322.62 |
| $84,001 – $85,000 | $1,333.12 |
| $85,001 – $86,000 | $1,343.62 |
| $86,001 – $87,000 | $1,354.12 |
| $87,001 – $88,000 | $1,364.62 |
| $88,001 – $89,000 | $1,375.12 |
| $89,001 – $90,000 | $1,385.62 |
| $90,001 – $91,000 | $1,396.12 |
| $91,001 – $92,000 | $1,406.62 |
| $92,001 – $93,000 | $1,417.12 |
| $93,001 – $94,000 | $1,427.62 |
| $94,001 – $95,000 | $1,438.12 |
| $95,001 – $96,000 | $1,448.62 |
| $96,001 – $97,000 | $1,459.12 |
| $97,001 – $98,000 | $1,469.62 |
| $98,001 – $99,000 | $1,480.12 |
| $99,001 – $100,000 | $1,490.62 |
| $100,001 – $500,000 | $1,490.62 for the first $100,000 + $11.20 per additional $1,000 or fraction |
| $500,001 – $1,000,000 | $5,970.62 for the first $500,000 + $9.50 per additional $1,000 or fraction |
| Over $1,000,000 | $10,720.62 for the first $1,000,000 + $6.30 per additional $1,000 or fraction |
What counts as project value
Your contract or bid price. The fee page and calculator use the 'Total Project Valuation' entered by the applicant; the fee sheet does not state how valuation is determined or checked.
Worked example: a $350,000 new home
- Building permit fee: $1,490.62 for the first $100,000.00 + $11.20 × 250 per $1,000.00 over = $4,290.62
- Plan review fee: 65% of $4,290.62 = $2,788.90
- Total before trade permits: $7,079.52.
Fees people miss
| Fee | Amount |
|---|---|
| ACH/E-Check transaction feeWhen: paying online by ACH/e-check | $1.80 each |
| Credit card transaction feeWhen: paying online by credit card | $3.20 percent |
| Site-specific development fees (RUTIF, Cherry Creek Drainage Basin Authority, RTIF)When: new buildings and additions in affected areas | |
| Open Space Sales and Use TaxWhen: collected with the permit as a sales/use tax on construction materials; amount depends on the materials share of valuation (the county says generally 50%) | 0.25% (0.0025) of the materials portion of the project valuation |
How to apply
- Gather your plans and your project's total value.
- Submit to Arapahoe County Public Works and Development, Building Division.
- Pay the permit and plan review fees when invoiced.