Building Permit Fees in Denver, CO (2026)

Denver prices building permits with a fee table based on project value, with a $20.00 minimum, then charges plan review at 0% up to $2,000, 50% above that of the permit fee. Enter your project to see the exact math.

  • Official city schedule
  • Effective not stated
  • Verified Nov 4, 2026
Minimum fee
$20.00
Plan review
50%
$75k addition
$893

Permit fee calculator

Denver schedule
Project type
Estimated permit fees $892.50
  1. 1. Building permit fee
    $420.00 for the first $50,000.00 + $7.00 × 25 per $1,000.00 over
    $595.00
  2. 2. Plan review fee
    50% of $595.00
    $297.50

May also apply (not in the total)

  • Two phase construction permits
    When: Only for two-phase (footing/foundation or podium/superstructure) permits; not available for single-family, duplex or townhomes
    $223.13
  • Three or more phase construction permits
    When: Only for three-or-more-phase permits; not available for single-family, duplex or townhomes
    $446.25

Fees are estimates based on the official schedule linked below. Confirm with the permit office before applying. Separate electrical, plumbing, mechanical, fire, impact, utility and school fees are usually not included unless they are listed. BuildingPermitCost is not a government permit office, and this is not legal advice.

What common projects cost

Kitchen or bath remodel
$25,000 value, remodel 300 sq ft
$328.50
$219.00 building permit + $109.50 plan review
Room addition
$75,000 value, addition 400 sq ft
$892.50
$595.00 building permit + $297.50 plan review
New single-family home
$350,000 value, new single-family 2,400 sq ft
$3,255.00
$2,170.00 building permit + $1,085.00 plan review

How Denver calculates your permit fee

The city charges a building permit fee using a fee table based on project value, with a $20.00 minimum. Plan review is a separate charge: 0% up to $2,000, 50% above that of the permit fee.

The fee table

Project valueFee
$1 – $500$20.00
$501 – $2,000$35.00
$2,001 – $25,000$35.00 for the first $2,000 + $8.00 per additional $1,000 or fraction
$25,001 – $50,000$220.00 for the first $25,000 + $8.00 per additional $1,000 or fraction
$50,001 – $100,000$420.00 for the first $50,000 + $7.00 per additional $1,000 or fraction
$100,001 – $500,000$770.00 for the first $100,000 + $5.60 per additional $1,000 or fraction
$500,001 – $1,000,000$3,010.00 for the first $500,000 + $4.75 per additional $1,000 or fraction
Over $1,000,000$5,385.00 for the first $1,000,000 + $3.65 per additional $1,000 or fraction

What counts as project value

Higher of your bid or the valuation table. Valuation is the total value of all construction work (labor, materials, profit, overhead, MEP, elevators, permanent equipment). It is the higher of the current ICC Building Valuation Data or the applicant's stated value. Townhouses: ICC BVD R-2 VB x residence sq ft (incl. basement) + U VB x garage sq ft, times 0.70. Table 2 local values: finished basement with toilet/kitchen $35/sq ft, without $31/sq ft; pop-top $105/sq ft; residential interior renovation $60/sq ft; quick permits: residential shingle roofs $5.25/sq ft, commercial low-slope roofs $7.25/sq ft.

Worked example: a $350,000 new home

  1. Building permit fee: $770.00 for the first $100,000.00 + $5.60 × 250 per $1,000.00 over = $2,170.00
  2. Plan review fee: 50% of $2,170.00 = $1,085.00
  3. Total before trade permits: $3,255.00.

Fees people miss

May also apply (not in the totals above)

  • Two phase construction permits: when Only for two-phase (footing/foundation or podium/superstructure) permits; not available for single-family, duplex or townhomes; $82.13 on the standard projects.
  • Three or more phase construction permits: when Only for three-or-more-phase permits; not available for single-family, duplex or townhomes; $164.25 on the standard projects.
FeeAmount
Additional plan review (incomplete, deferred or modified drawings; third review cycle)When: Only when additional review is triggered $125.00 per hour
Reinspection, after-hours and non-customary inspectionsWhen: Only on reinspection or special inspection $100.00 per hour
Alternate materials/methods or administrative modification application $125.00 per hour
Board of Appeals hearing application $250.00 each
Permit change of contractor $100.00 each
Temporary certificate of occupancy $200.00 each
Forestry plan review & inspection $65.00 each
Contractor license (A, B, C, D) $250.00 every 3 years

How to apply

  1. Gather your plans and your project's total value.
  2. Submit to Community Planning and Development (CPD).
  3. Pay the permit and plan review fees when invoiced.

How Denver compares

A $25,000 remodel costs $328.50 in Denver: 14% below the national median of $380.00, and the 3rd lowest of 15 places we cover in Colorado (state median $531.00).

A $75,000 addition costs $892.50 in Denver: 9% above the national median of $820.58, and the 6th lowest of 15 places we cover in Colorado (state median $1,174.21).

A $350,000 new home costs $3,255.00 in Denver: 12% above the national median of $2,918.63, and the 5th lowest of 15 places we cover in Colorado (state median $3,972.62).

Same standard projects everywhere, including plan review and required surcharges. All Colorado places · Compare side by side

Denver permit fee FAQ

How much is a building permit in Denver, CO?

A $25,000 remodel: $328.50. A $75,000 addition: $892.50. A $350,000 new single-family: $3,255.00. These include every fee the schedule applies to that project; trade permits are separate.

Is plan review included in the Denver permit fee?

No. Plan review is charged separately at 0% up to $2,000, 50% above that of the permit fee.

How does Denver determine project value?

Higher of your bid or the valuation table. Valuation is the total value of all construction work (labor, materials, profit, overhead, MEP, elevators, permanent equipment). It is the higher of the current ICC Building Valuation Data or the applicant's stated value. Townhouses: ICC BVD R-2 VB x residence sq ft (incl. basement) + U VB x garage sq ft, times 0.70. Table 2 local values: finished basement with toilet/kitchen $35/sq ft, without $31/sq ft; pop-top $105/sq ft; residential interior renovation $60/sq ft; quick permits: residential shingle roofs $5.25/sq ft, commercial low-slope roofs $7.25/sq ft.

When did these Denver fees take effect?

The schedule does not state an effective date. We last checked it against the official source on Nov 4, 2026.