BuildingPermitCost

Building Permit Fees in Centennial, CO (2026)

Centennial prices building permits with a fee table based on project value, with a $23.50 minimum, then charges plan review at 65% of the permit fee. Enter your project to see the exact math.

  • Official city schedule
  • Effective not stated
  • Verified Nov 5, 2026
Minimum fee
$23.50
Plan review
65%
$75k addition
$1,351

Permit fee calculator

Centennial schedule
Project type
Estimated permit fees $1,350.94
  1. 1. Building permit fee
    $643.75 for the first $50,000.00 + $7.00 × 25 per $1,000.00 over
    $818.75
  2. 2. Plan review fee
    65% of $818.75
    $532.19

Fees are estimates based on the official schedule linked below. Confirm with the permit office before applying. Separate electrical, plumbing, mechanical, fire, impact, utility and school fees are usually not included unless they are listed. BuildingPermitCost is not a government permit office, and this is not legal advice.

What common projects cost

Kitchen or bath remodel
$25,000 value, remodel 300 sq ft
$645.56
$391.25 building permit + $254.31 plan review
Room addition
$75,000 value, addition 400 sq ft
$1,350.94
$818.75 building permit + $532.19 plan review
New single-family home
$350,000 value, new single-family 2,400 sq ft
$3,949.69
$2,393.75 building permit + $1,555.94 plan review

How Centennial calculates your permit fee

The city charges a building permit fee using a fee table based on project value, with a $23.50 minimum. Plan review is a separate charge: 65% of the permit fee. Electrical, plumbing and mechanical work gets its own permits.

The fee table

Project valueFee
$1 – $500$23.50
$501 – $2,000$23.50 for the first $500 + $3.05 per additional $100 or fraction
$2,001 – $25,000$69.25 for the first $2,000 + $14.00 per additional $1,000 or fraction
$25,001 – $50,000$391.25 for the first $25,000 + $10.10 per additional $1,000 or fraction
$50,001 – $100,000$643.75 for the first $50,000 + $7.00 per additional $1,000 or fraction
$100,001 – $500,000$993.75 for the first $100,000 + $5.60 per additional $1,000 or fraction
$500,001 – $1,000,000$3,233.75 for the first $500,000 + $4.75 per additional $1,000 or fraction
Over $1,000,000$5,608.75 for the first $1,000,000 + $3.15 per additional $1,000 or fraction

What counts as project value

Your contract or bid price. Valuation is determined by the building official: 'the total value of all construction work for which the permit is issued, as well as all finish work, painting, roofing, electrical, plumbing, heating, air conditioning...'.

Worked example: a $350,000 new home

  1. Building permit fee: $993.75 for the first $100,000.00 + $5.60 × 250 per $1,000.00 over = $2,393.75
  2. Plan review fee: 65% of $2,393.75 = $1,555.94
  3. Total before trade permits: $3,949.69.

Fees people miss

FeeAmount
Inspections outside normal business hoursWhen: after-hours inspection requested $125.00 per hour, minimum 2 hours (or total hourly cost if greater)
Re-inspectionWhen: re-inspection required $55.00 per hour
Inspections with no fee specifically indicatedWhen: other inspections $55.00 per hour, minimum one half hour
Additional plan review (changes, additions, revisions)When: plan revisions or deferred submittals $55.00 per hour, minimum one half hour
Temporary Certificate of OccupancyWhen: TCO requested $800.00 each
Paper plan submittal surcharge (commercial only)When: commercial plans submitted on paper $3.00 per page
Outside consultant plan check/inspectionWhen: outside consultant used actual cost
City building materials use tax deposit 2.5% of 50% of valuation
Arapahoe County use tax deposit 0.25% of 50% of valuation

Trade permits are separate. Electrical: Residential (by living area): up to 1,000 sq ft $100; 1,001-1,500 $150; 1,501-2,000 $200; plus $10 per 100 sq ft (rounded up) over 2,000. Other electrical: $100 up to $2,000 of installation cost, then $5 per $1,000 or fraction + $100.

How to apply

  1. Gather your plans and your project's total value.
  2. Submit to City of Centennial Building Division.
  3. Pay the permit and plan review fees when invoiced.
  4. Questions: 303-754-3321 · 13133 E. Arapahoe Rd., Centennial, CO 80112

How Centennial compares

A $25,000 remodel costs $645.56 in Centennial: 70% above the national median of $380.00, and the 6th highest of 15 places we cover in Colorado (state median $531.00).

A $75,000 addition costs $1,350.94 in Centennial: 65% above the national median of $820.58, and the 5th highest of 15 places we cover in Colorado (state median $1,174.21).

A $350,000 new home costs $3,949.69 in Centennial: 35% above the national median of $2,918.63, and the 7th lowest of 15 places we cover in Colorado (state median $3,972.62).

Same standard projects everywhere, including plan review and required surcharges. All Colorado places · Compare side by side

Centennial permit fee FAQ

How much is a building permit in Centennial, CO?

A $25,000 remodel: $645.56. A $75,000 addition: $1,350.94. A $350,000 new single-family: $3,949.69. These include every fee the schedule applies to that project; trade permits are separate.

Is plan review included in the Centennial permit fee?

No. Plan review is charged separately at 65% of the permit fee.

How does Centennial determine project value?

Your contract or bid price. Valuation is determined by the building official: 'the total value of all construction work for which the permit is issued, as well as all finish work, painting, roofing, electrical, plumbing, heating, air conditioning...'.

Are electrical, plumbing and mechanical permits included?

No. They are separate permits. Electrical: Residential (by living area): up to 1,000 sq ft $100; 1,001-1,500 $150; 1,501-2,000 $200; plus $10 per 100 sq ft (rounded up) over 2,000. Other electrical: $100 up to $2,000 of installation cost, then $5 per $1,000 or fraction + $100.

When did these Centennial fees take effect?

The schedule does not state an effective date. We last checked it against the official source on Nov 5, 2026.