How Alexandria calculates your permit fee
The city charges a building permit fee using $0.75 per square foot, with a $95.00 minimum. Electrical, plumbing and mechanical work gets its own permits.
The fee table
Residential new construction (Virginia Residential Code)
$0.75 per square foot, with a $95.00 minimum.
Residential · remodels and alterations
$0.30 per square foot, or $18.00 per $1,000 of project value, whichever is greater, with a $95.00 minimum.
Commercial · new construction, additions
$7.50 per $1,000 of project value, with a $95.00 minimum.
Commercial · remodels and alterations
$0.48 per square foot, or $19.75 per $1,000 of project value, whichever is greater, with a $95.00 minimum.
Added to every matching permit
- Electrical permit, new residential unit: a flat $194.00 (Residential · new construction)
- Plumbing permit, new residential unit: a flat $194.00 (Residential · new construction)
- Mechanical permit, new residential unit: a flat $194.00 (Residential · new construction)
- Residential certificate of occupancy (per dwelling unit): a flat $156.75 (Residential · new construction)
Surcharges
- Administrative fee: 14% of the fee total
- Permit Center fee: 11% of the fee total
- Information technology fee: 5% of the fee total
- Training program fee: 0.2% of the fee total
What counts as project value
Floor area (square feet). Residential new construction is priced per square foot (including basements, garages, roofed carports). Valuation-based fees use the total contract price (labor and materials at retail market value plus overhead and profit); new construction cost is computed from ICC Building Valuation Data Table 1 x gross area.
Worked example: a $350,000 new home
- Building permit fee: 2,400 sq ft × $0.75 = $1,800.00
- Electrical permit, new residential unit: flat fee = $194.00
- Plumbing permit, new residential unit: flat fee = $194.00
- Mechanical permit, new residential unit: flat fee = $194.00
- Residential certificate of occupancy (per dwelling unit): flat fee = $156.75
- Administrative fee: 14% of $2,538.75 = $355.43
- Permit Center fee: 11% of $2,894.18 = $318.36
- Information technology fee: 5% of $3,212.54 = $160.63
- Training program fee: 0.2% of $3,373.17 = $6.75
- Total before trade permits: $3,379.92.
Fees people miss
| Fee | Amount |
|---|---|
| Permit application deposit | 35% of total estimated permit fee (credited) |
| Plan revision/resubmittal, new constructionWhen: revisions after approval or beyond one resubmittal | $100.00 per trade discipline |
| Plan revision/resubmittal, alterationsWhen: revisions | $50.00 per trade discipline |
| Advanced plan review (residential)When: optional pre-permit review | $0.05 per sq ft, max $10,000 |
| Virginia Training Academy levy | state levy on all permit fees |
| Payment processing feeWhen: card/electronic payment | vendor rate |
Trade permits are separate. Electrical: New residential unit $194; alterations/additions $19.50 per $1,000 or minimum $95, whichever greater; service equipment first 200 A $92. Plumbing: New residential unit $194; alterations/additions $19.50 per $1,000 or minimum. Mechanical: New residential unit $194; alterations/additions $19.50 per $1,000 or minimum. Gas piping base $40 residential + $20 per outlet.
How to apply
- Gather your plans and your project's total value and floor area.
- Submit to Department of Code Administration - Alexandria Permit Center through APEX.
- Pay the permit and plan review fees when invoiced.