How Rockville calculates your permit fee
The city charges a building permit fee using $0.35 per square foot, plus a $290.00 application fee, with a $145.00 minimum. Electrical, plumbing and mechanical work gets its own permits.
The fee table
Residential new dwelling (IRC)
$0.35 per square foot, plus a $290.00 application fee, with a $145.00 minimum.
Residential addition (IRC)
$0.35 per square foot, plus a $145.00 application fee, with a $145.00 minimum.
Residential alterations and repairs (IRC)
$0.35 per square foot, plus a $145.00 application fee, with a $145.00 minimum.
Commercial/multi-family new construction
$0.50 per square foot, or 1.8% of project value, whichever is greater, plus a $175.00 application fee, with a $175.00 minimum.
Commercial/multi-family alteration and repair
$0.45 per square foot, or 1.7% of project value, whichever is greater, plus a $175.00 application fee, with a $175.00 minimum.
Surcharges
- Automation fee: 10.25% of the fee total
What counts as project value
Floor area (square feet). Residential fees are per square foot 'including basement, each floor, garage and roof' (new/additions) or 'of affected area' (alterations). Commercial: per square foot or a percentage of 'the total construction costs as estimated by the Building Official, whichever is greater'.
Worked example: a $350,000 new home
- Building permit fee: 2,400 sq ft × $0.35 = $840.00
- Application fee: fixed = $290.00
- Automation fee: 10.25% of $1,130.00 = $115.83
- Total before trade permits: $1,245.83.
Fees people miss
May also apply (not in the totals above)
- Occupancy permit (per dwelling unit): when an occupancy permit is issued for the new dwelling; $125.00 on the standard projects.
| Fee | Amount |
|---|---|
| Amendments, one- and two-family residential (third and subsequent reviews)When: third or later review | $100.00 per review |
| Amendments/revisions, commercial and multifamilyWhen: additional review | 50% of original permit fee or $175, whichever is greater (max $2,430) |
| Administrative amendment to existing permitWhen: amendment requested | $45.00 per request |
| Permit extension (unexpired permit)When: extension requested | $70.00 per request |
| Inspector callback for re-inspectionWhen: re-inspection | $130.00 per request, per permit |
| Overtime inspectionsWhen: overtime inspection | $265.00 per inspection per inspector |
| Investigation of work without a permit (owner, residential)When: work started without permit | $205.00 per trade |
| Commercial occupancyWhen: commercial occupancy permit | $175.00 per 5,000 sq ft or fraction |
Trade permits are separate. Electrical: Minimum $80; rough wiring 1-20 outlets $80, each additional 20 $20; fixtures 1-20 $80, each additional 20 $20; services from $100. Automation fee 10.25% added. Mechanical: Minimum $75; first mechanical unit $75, each additional unit $20. Automation fee 10.25% added. Plumbing: Minimum $80; first fixture $80, each additional fixture $20. Water meter and capital contribution fees separate. Automation fee 10.25% added (excludes capital contribution and water meter fees).
How to apply
- Gather your plans and your project's total value and floor area.
- Submit to Inspection Services Division online through the permit portal.
- Pay the permit and plan review fees when invoiced.