Rockville prices building permits with $0.35 per square foot, plus a $290.00 application fee, with a $145.00 minimum. Enter your project to see the exact math.

  • Official city schedule
  • Effective Jul 1, 2026
  • Verified Nov 5, 2026
Minimum fee
$145.00
Plan review
None
$75k addition
$320

Permit fee calculator

Rockville schedule, eff. Jul 1, 2026
Project type
Estimated permit fees $319.73
  1. 1. Building permit fee
    400 sq ft × $0.35 → minimum $145.00
    $145.00
  2. 2. Application fee
    fixed
    $145.00
  3. 3. Automation fee
    10.25% of $290.00
    $29.73

Fees are estimates based on the official schedule linked below. Confirm with the permit office before applying. Separate electrical, plumbing, mechanical, fire, impact, utility and school fees are usually not included unless they are listed. BuildingPermitCost is not a government permit office, and this is not legal advice.

What common projects cost

Kitchen or bath remodel
$25,000 value, remodel 300 sq ft
$319.73
$145.00 building permit + $145.00 application + $29.73 automation
Room addition
$75,000 value, addition 400 sq ft
$319.73
$145.00 building permit + $145.00 application + $29.73 automation
New single-family home
$350,000 value, new single-family 2,400 sq ft
$1,245.83
$840.00 building permit + $290.00 application + $115.83 automation

How Rockville calculates your permit fee

The city charges a building permit fee using $0.35 per square foot, plus a $290.00 application fee, with a $145.00 minimum. Electrical, plumbing and mechanical work gets its own permits.

The fee table

Residential new dwelling (IRC)

$0.35 per square foot, plus a $290.00 application fee, with a $145.00 minimum.

Residential addition (IRC)

$0.35 per square foot, plus a $145.00 application fee, with a $145.00 minimum.

Residential alterations and repairs (IRC)

$0.35 per square foot, plus a $145.00 application fee, with a $145.00 minimum.

Commercial/multi-family new construction

$0.50 per square foot, or 1.8% of project value, whichever is greater, plus a $175.00 application fee, with a $175.00 minimum.

Commercial/multi-family alteration and repair

$0.45 per square foot, or 1.7% of project value, whichever is greater, plus a $175.00 application fee, with a $175.00 minimum.

Surcharges

  • Automation fee: 10.25% of the fee total

What counts as project value

Floor area (square feet). Residential fees are per square foot 'including basement, each floor, garage and roof' (new/additions) or 'of affected area' (alterations). Commercial: per square foot or a percentage of 'the total construction costs as estimated by the Building Official, whichever is greater'.

Worked example: a $350,000 new home

  1. Building permit fee: 2,400 sq ft × $0.35 = $840.00
  2. Application fee: fixed = $290.00
  3. Automation fee: 10.25% of $1,130.00 = $115.83
  4. Total before trade permits: $1,245.83.

Fees people miss

May also apply (not in the totals above)

  • Occupancy permit (per dwelling unit): when an occupancy permit is issued for the new dwelling; $125.00 on the standard projects.
FeeAmount
Amendments, one- and two-family residential (third and subsequent reviews)When: third or later review $100.00 per review
Amendments/revisions, commercial and multifamilyWhen: additional review 50% of original permit fee or $175, whichever is greater (max $2,430)
Administrative amendment to existing permitWhen: amendment requested $45.00 per request
Permit extension (unexpired permit)When: extension requested $70.00 per request
Inspector callback for re-inspectionWhen: re-inspection $130.00 per request, per permit
Overtime inspectionsWhen: overtime inspection $265.00 per inspection per inspector
Investigation of work without a permit (owner, residential)When: work started without permit $205.00 per trade
Commercial occupancyWhen: commercial occupancy permit $175.00 per 5,000 sq ft or fraction

Trade permits are separate. Electrical: Minimum $80; rough wiring 1-20 outlets $80, each additional 20 $20; fixtures 1-20 $80, each additional 20 $20; services from $100. Automation fee 10.25% added. Mechanical: Minimum $75; first mechanical unit $75, each additional unit $20. Automation fee 10.25% added. Plumbing: Minimum $80; first fixture $80, each additional fixture $20. Water meter and capital contribution fees separate. Automation fee 10.25% added (excludes capital contribution and water meter fees).

How to apply

  1. Gather your plans and your project's total value and floor area.
  2. Submit to Inspection Services Division online through the permit portal.
  3. Pay the permit and plan review fees when invoiced.

How Rockville compares

A $25,000 remodel costs $319.73 in Rockville: 16% below the national median of $380.00.

A $75,000 addition costs $319.73 in Rockville: 61% below the national median of $820.58.

A $350,000 new home costs $1,245.83 in Rockville: 57% below the national median of $2,918.63.

Same standard projects everywhere, including plan review and required surcharges. All Maryland places · Compare side by side

Rockville permit fee FAQ

How much is a building permit in Rockville, MD?

A $25,000 remodel: $319.73. A $75,000 addition: $319.73. A $350,000 new single-family: $1,245.83. These include every fee the schedule applies to that project; trade permits are separate.

Is plan review included in the Rockville permit fee?

Rockville lists no separate plan review fee for these projects.

How does Rockville determine project value?

Floor area (square feet). Residential fees are per square foot 'including basement, each floor, garage and roof' (new/additions) or 'of affected area' (alterations). Commercial: per square foot or a percentage of 'the total construction costs as estimated by the Building Official, whichever is greater'.

Are electrical, plumbing and mechanical permits included?

No. They are separate permits. Electrical: Minimum $80; rough wiring 1-20 outlets $80, each additional 20 $20; fixtures 1-20 $80, each additional 20 $20; services from $100. Automation fee 10.25% added. Mechanical: Minimum $75; first mechanical unit $75, each additional unit $20. Automation fee 10.25% added. Plumbing: Minimum $80; first fixture $80, each additional fixture $20. Water meter and capital contribution fees separate. Automation fee 10.25% added (excludes capital contribution and water meter fees).

When did these Rockville fees take effect?

The schedule is effective Jul 1, 2026 (“Fee Schedule Effective July 1, 2026, Revised September 14, 2026 (FY 2027)”). We last checked it against the official source on Nov 5, 2026.