How Chandler calculates your permit fee
The city charges a building permit fee using a fee table based on project value, with a $50.00 minimum. Plan review is a separate charge: 65% of the permit fee.
The fee table
| Project value | Fee |
|---|---|
| $1 – $500 | $50.00 |
| $501 – $2,000 | $50.00 for the first $500 + $1.20 per additional $100 or fraction |
| $2,001 – $25,000 | $68.00 for the first $2,000 + $12.50 per additional $1,000 or fraction |
| $25,001 – $50,000 | $355.50 for the first $25,000 + $9.00 per additional $1,000 or fraction |
| $50,001 – $100,000 | $580.50 for the first $50,000 + $6.25 per additional $1,000 or fraction |
| $100,001 – $500,000 | $893.00 for the first $100,000 + $5.00 per additional $1,000 or fraction |
| $500,001 – $1,000,000 | $2,893.00 for the first $500,000 + $4.25 per additional $1,000 or fraction |
| Over $1,000,000 | $5,018.00 for the first $1,000,000 + $2.75 per additional $1,000 or fraction |
What counts as project value
ICC Building Valuation Data table. New construction: most current ICC Building Valuation Data. Alterations: all construction costs involved, approved by the Building Official.
Worked example: a $350,000 new home
- Building permit fee: $893.00 for the first $100,000.00 + $5.00 × 250 per $1,000.00 over = $2,143.00
- Plan review fee: 65% of $2,143.00 = $1,392.95
- Total before trade permits: $3,535.95.
Fees people miss
May also apply (not in the totals above)
- Foundation only permit: when foundation-only permit requested; $88.88 on the standard projects.
| Fee | Amount |
|---|---|
| Expedited plan reviewWhen: expedited review at Building Official's discretion | twice the normal plan review fee |
| Additional revisions to approved plansWhen: plan revisions | $60.00 per hour |
| Deferred submittal itemsWhen: deferred submittals | $60.00 per hour |
| Re-inspectionWhen: failed inspection | $60.00 per hour |
| Inspection outside normal business hoursWhen: after hours | $75.00 per hour |
| Administrative fee for permits from approved standard plansWhen: permit from approved standard plans | $75.00 each |
| Certificate of Occupancy not associated with a building permitWhen: CO without building permit | $100.00 each |
| Temporary Certificate of OccupancyWhen: temporary CO | $100.00 first 30 days |
| Permit reinstatement (within one year of expiration)When: expired permit | 50% of current permit fee |
| Annual Facility PermitWhen: annual facility permit | $1,000.00 registration |
| Permit issuance when no other fees applyWhen: no other fees apply | $60.00 each |
How to apply
- Gather your plans and your project's total value.
- Submit to City of Chandler Development Services, Building Safety.
- Pay the permit and plan review fees when invoiced.