How Frisco calculates your permit fee
The city charges a building permit fee using a fee table based on floor area, plus a $300.00 application fee. Electrical, plumbing and mechanical work gets its own permits.
The fee table
Residential new construction and addition
| Floor area | Fee |
|---|---|
| 0 sq ft – 300 sq ft | $150.00 |
| 300 sq ft – 2,000 sq ft | $150.00 for the first 300 sq ft + $0.50 per additional sq ft or fraction |
| 2,000 sq ft – 2,500 sq ft | $1,000.00 for the first 2,000 sq ft + $0.37 per additional sq ft or fraction |
| 2,500 sq ft – 3,000 sq ft | $1,185.00 for the first 2,500 sq ft + $0.35 per additional sq ft or fraction |
| 3,000 sq ft – 3,500 sq ft | $1,360.00 for the first 3,000 sq ft + $0.34 per additional sq ft or fraction |
| 3,500 sq ft – 4,000 sq ft | $1,530.00 for the first 3,500 sq ft + $0.33 per additional sq ft or fraction |
| 4,000 sq ft – 4,500 sq ft | $1,695.00 for the first 4,000 sq ft + $0.32 per additional sq ft or fraction |
| 4,500 sq ft – 5,000 sq ft | $1,855.00 for the first 4,500 sq ft + $0.31 per additional sq ft or fraction |
| 5,000 sq ft – 5,500 sq ft | $2,010.00 for the first 5,000 sq ft + $0.30 per additional sq ft or fraction |
| 5,500 sq ft – 6,000 sq ft | $2,160.00 for the first 5,500 sq ft + $0.29 per additional sq ft or fraction |
| 6,000 sq ft – 6,500 sq ft | $2,305.00 for the first 6,000 sq ft + $0.29 per additional sq ft or fraction |
| 6,500 sq ft – 7,000 sq ft | $2,450.00 for the first 6,500 sq ft + $0.28 per additional sq ft or fraction |
| Over 7,000 sq ft | $2,590.00 for the first 7,000 sq ft + $0.26 per additional sq ft or fraction |
Plus an application fee of $300.00.
Residential general alterations
| Floor area | Fee |
|---|---|
| Over 0 sq ft | $75.00 + $0.45 per additional sq ft or fraction |
Plus an application fee of $50.00.
What counts as project value
Floor area (square feet). Residential new construction, additions and alterations are priced by gross square feet ('Square feet are measured as gross'). Commercial permits use a valuation table (Table 1-A) at 80% of the table value; the schedule does not say how valuation is determined.
Worked example: a $350,000 new home
- Building permit fee: $1,000.00 for the first 2,000 sq ft + $0.37 × 400 per sq ft over = $1,148.00
- Application fee: fixed = $300.00
- Total before trade permits: $1,448.00.
Fees people miss
| Fee | Amount |
|---|---|
| Commercial non-refundable application feeWhen: commercial permits | $300.00 each |
| Inspection outside normal business hoursWhen: after hours | $150.00 each |
| Reinspection fee (residential)When: reinspection | $50.00 each |
| Plan revision reviewWhen: plan revision | $50.00 per hour |
| Work commencing without a permit (non-emergency)When: work started without permit | double permit fee |
| Certificate of Occupancy (change of business name, ownership or use)When: commercial change | $100.00 each |
| Temporary Certificate of OccupancyWhen: temporary CO | $500.00 each |
Trade permits are separate. Electrical: $50 issuance per permit; all-inclusive residential permit by square footage $0.03/gsf (commercial $0.04/gsf); itemised appliance, motor and service fees. Mechanical: $50 issuance per permit; new finish-out/alterations $0.05/gsf; itemised appliance fees. Plumbing: $50 issuance per permit; new finish-out/alteration $0.09/gsf; $7 per fixture and itemised fees.
How to apply
- Gather your plans and your project's total value and floor area.
- Submit to City of Frisco Development Services / Building Inspections.
- Pay the permit and plan review fees when invoiced.