Building Permit Fees in Ann Arbor, MI (2026)

Ann Arbor prices building permits with a fee table based on project value, plus a $15.00 application fee, with a $100.00 minimum, then charges plan review at 20% of the permit fee. Enter your project to see the exact math.

  • Official city schedule
  • Effective not stated
  • Verified Nov 5, 2026
Minimum fee
$100.00
Plan review
20%
$75k addition
$945

Permit fee calculator

Ann Arbor schedule
Project type
Estimated permit fees $945.00
  1. 1. Building permit fee
    $550.00 for the first $50,000.00 + $9.00 × 25 per $1,000.00 over
    $775.00
  2. 2. Application fee
    fixed
    $15.00
  3. 3. Plan review fee
    20% of $775.00
    $155.00

May also apply (not in the total)

  • Zoning Compliance permit
    When: the project requires a Zoning Compliance permit (listed for building projects on the building fee sheet)
    $75.00
  • Trades plan examination fee
    When: trade (electrical, mechanical, plumbing) plans are examined with the building plans
    $38.75

Fees are estimates based on the official schedule linked below. Confirm with the permit office before applying. Separate electrical, plumbing, mechanical, fire, impact, utility and school fees are usually not included unless they are listed. BuildingPermitCost is not a government permit office, and this is not legal advice.

What common projects cost

Kitchen or bath remodel
$25,000 value, remodel 300 sq ft
$435.00
$350.00 building permit + $15.00 application + $70.00 plan review
Room addition
$75,000 value, addition 400 sq ft
$945.00
$775.00 building permit + $15.00 application + $155.00 plan review
New single-family home
$350,000 value, new single-family 2,400 sq ft
$3,705.00
$3,075.00 building permit + $15.00 application + $615.00 plan review

How Ann Arbor calculates your permit fee

The city charges a building permit fee using a fee table based on project value, plus a $15.00 application fee, with a $100.00 minimum. Plan review is a separate charge: 20% of the permit fee. Electrical, plumbing and mechanical work gets its own permits.

The fee table

Project valueFee
$1 – $1,000$100.00
$1,001 – $50,000$110.00 for the first $1,000 + $10.00 per additional $1,000
$50,001 – $100,000$550.00 for the first $50,000 + $9.00 per additional $1,000
$100,001 – $500,000$950.00 for the first $100,000 + $8.50 per additional $1,000
$500,001 – $1,000,000$4,100.00 for the first $500,000 + $8.00 per additional $1,000
Over $1,000,000$7,600.00 for the first $1,000,000 + $7.50 per additional $1,000

Plus an application fee of $15.00.

What counts as project value

Your contract or bid price. Permit fee is 'Based on estimated project cost' (applicant's estimated cost of the work). No ICC/local valuation table is cited.

Worked example: a $350,000 new home

  1. Building permit fee: $950.00 for the first $100,000.00 + $8.50 × 250 per $1,000.00 over = $3,075.00
  2. Application fee: fixed = $15.00
  3. Plan review fee: 20% of $3,075.00 = $615.00
  4. Total before trade permits: $3,705.00.

Fees people miss

May also apply (not in the totals above)

  • Zoning Compliance permit: when the project requires a Zoning Compliance permit (listed for building projects on the building fee sheet); $75.00 on the standard projects.
  • Trades plan examination fee: when trade (electrical, mechanical, plumbing) plans are examined with the building plans; $17.50 on the standard projects.
FeeAmount
Contractor registration or re-registrationWhen: contractor registration $15.00 each
Revised plans after approval (substantial changes)When: revised plans submitted after approval $100.00 minimum
Each inspection (extra inspections at Building Official's discretion)When: extra inspections charged $35.00 each
Special or overtime inspectionWhen: special or overtime inspection requested $130.00 minimum
Historic district staff reviewWhen: property located in a historic district $35.00 each
Site Compliance PermitWhen: site compliance permit required $150.00 each
Site Compliance InspectionWhen: site compliance permit required $60.00 each
Certificate of Occupancy, change of occupancy (commercial) / change of useWhen: change of occupancy or use $170.00 each
Temporary Certificate of Occupancy or renewalWhen: temporary CO requested $30.00 each
Vacant building postingWhen: vacant building $100.00 each
Permit reactivationWhen: expired permit reactivated $35.00 each

Trade permits are separate. Electrical: Separate Electrical fee sheet (2020) and Fire Alarm sheet (2017); not extracted. Plumbing: Separate Plumbing fee sheet (2017); not extracted. Mechanical: Separate Mechanical (2017) and Fire Suppression sheets; not extracted.

How to apply

  1. Gather your plans and your project's total value.
  2. Submit to Building, Rental and Inspection Services (Building and Construction Services) online through STREAM.
  3. Pay the permit and plan review fees when invoiced.
  4. Questions: 734-794-6263 ext. 0 · City Hall, 301 E. Huron Street, Ann Arbor, MI 48104

How Ann Arbor compares

A $25,000 remodel costs $435.00 in Ann Arbor: 14% above the national median of $380.00.

A $75,000 addition costs $945.00 in Ann Arbor: 15% above the national median of $820.58.

A $350,000 new home costs $3,705.00 in Ann Arbor: 27% above the national median of $2,918.63.

Same standard projects everywhere, including plan review and required surcharges. All Michigan places · Compare side by side

Ann Arbor permit fee FAQ

How much is a building permit in Ann Arbor, MI?

A $25,000 remodel: $435.00. A $75,000 addition: $945.00. A $350,000 new single-family: $3,705.00. These include every fee the schedule applies to that project; trade permits are separate.

Is plan review included in the Ann Arbor permit fee?

No. Plan review is charged separately at 20% of the permit fee.

How does Ann Arbor determine project value?

Your contract or bid price. Permit fee is 'Based on estimated project cost' (applicant's estimated cost of the work). No ICC/local valuation table is cited.

Are electrical, plumbing and mechanical permits included?

No. They are separate permits. Electrical: Separate Electrical fee sheet (2020) and Fire Alarm sheet (2017); not extracted. Plumbing: Separate Plumbing fee sheet (2017); not extracted. Mechanical: Separate Mechanical (2017) and Fire Suppression sheets; not extracted.

When did these Ann Arbor fees take effect?

The schedule does not state an effective date. We last checked it against the official source on Nov 5, 2026.