How DuPage County calculates your permit fee
The county charges a building permit fee using a fee table based on project value, with a $50.00 minimum. Plan review is a separate charge: its own fee table. Electrical, plumbing and mechanical work gets its own permits.
The fee table
Single family / townhomes, new construction and additions
| Project value | Fee |
|---|---|
| Over $0 | $10.00 per $1,000 or fraction |
Single family / townhomes, remodeling
| Project value | Fee |
|---|---|
| Over $0 | $10.00 per $1,000 or fraction |
Industrial and commercial
| Project value | Fee |
|---|---|
| Over $0 | $30.00 per $1,000 or fraction |
Industrial and commercial, remodeling
| Project value | Fee |
|---|---|
| Over $0 | $30.00 per $1,000 or fraction |
What counts as project value
Higher of your bid or the valuation table. Valuation comes from the county's cost schedule (e.g. single-family new construction $90 per sq ft of all areas within outside walls; decks/patios $10/sq ft; accessory structures $10 or $30/sq ft); if the applicant's valuation is higher, the higher figure prevails. Remodeling is based on cost of construction.
Worked example: a $350,000 new home
- Building permit fee: $0.00 for the first $0.00 + $10.00 × 350 per $1,000.00 over = $3,500.00
- Plan review fee: table value for 2,400 sq ft: $235.00 = $235.00
- Total before trade permits: $3,735.00.
Fees people miss
May also apply (not in the totals above)
- Work started without a permit: when work started before permit issued; $250.00 on the standard projects.
| Fee | Amount |
|---|---|
| Drainage/grading review fee, residential | by disturbed ground area |
| Certificate of Use and Occupancy, single family | $100.00 each |
| Cash performance bond, residential new constructionWhen: refundable bond | $2,000.00 each |
| Plan resubmittal / revision review, Type I & IIWhen: resubmittal | $100.00 per resubmittal |
| Re-inspectionWhen: failed or not-ready inspection | $50.00 each |
| Conference feeWhen: second and subsequent meetings per project | $50.00 per hour per staff member |
| Outside consultant plan reviewWhen: when outside consultant review is required | consultant cost plus 20% administrative fee |
| Refund administrative feeWhen: permit refund | $50.00 each |
| Damage assessment (fire, wind, flood)When: damage assessment | $100.00 each |
Trade permits are separate. Plumbing: Minimum fee residential $50 / commercial $100; $15 per plumbing fixture. Electrical: Minimum residential $50 / commercial $100. Residential by square feet: 0-1,000 $50; 1,001-1,599 $60; 1,600-2,399 $70; 2,400-2,999 $80; 3,000+ $90. New service 100-199 A $50 up to 800 A+ $80 plus $10 per additional 100 A. Circuits (non-residential) $8/$10/$12 for 2/3/4-wire.
How to apply
- Gather your plans and your project's total value.
- Submit to DuPage County Building and Zoning through Accela Citizen Access.
- Pay the permit and plan review fees when invoiced.