Building Permit Fees in Fort Myers, FL (2026)

Fort Myers prices building permits with a fee table based on project value, then charges plan review at 30% of the permit fee (minimum $78.00). Enter your project to see the exact math.

  • Official city schedule
  • Effective Aug 5, 2025
  • Verified Nov 5, 2026
Minimum fee
—
Plan review
30%
$75k addition
—

Permit fee calculator

Fort Myers schedule, eff. Aug 5, 2025
Project type
Estimated permit fees $544.71
  1. 1. Building permit fee
    $101.00 for the first $0.00 + $12.04 × 25 per $1,000.00 over
    $402.00
  2. 2. Plan review fee
    30% of $402.00
    $120.60
  3. 3. Inspector's Trust
    1.5% of $402.00
    $6.03
  4. 4. Radon Tax
    1% of $402.00
    $4.02
  5. 5. Technology Fee (BPI)
    1.5% of $402.00
    $6.03
  6. 6. Technology Fee (General Fund)
    1.5% of $402.00
    $6.03

May also apply (not in the total)

  • Zoning plan review (alterations other than interior-only renovation)
    When: the alteration is not an interior renovation only (interior-only renovations pay $0)
    $75.00
  • Engineering plan review (alterations other than interior-only renovation)
    When: the alteration is not an interior renovation only (interior-only renovations pay $0)
    $100.00

Fees are estimates based on the official schedule linked below. Confirm with the permit office before applying. Separate electrical, plumbing, mechanical, fire, impact, utility and school fees are usually not included unless they are listed. BuildingPermitCost is not a government permit office, and this is not legal advice.

What common projects cost

Kitchen or bath remodel
$25,000 value, remodel 300 sq ft
$544.71
$402.00 building permit + $120.60 plan review + $6.03 inspector's trust + $4.02 radon tax + $6.03 technology fee (bpi) + $6.03 technology fee (general fund)
Room addition
$75,000 value, addition 400 sq ft
n/a
No building-permit formula for this project type.
New single-family home
$350,000 value, new single-family 2,400 sq ft
$3,882.80
$2,467.00 building permit + $740.10 plan review + $140.00 zoning plan review (residential/multi-family new construction) + $350.00 engineering plan review (residential/multi-family new construction) + $50.00 certificate of occupancy + $37.01 inspector's trust + $24.67 radon tax + $37.01 technology fee (bpi) + $37.01 technology fee (general fund)

How Fort Myers calculates your permit fee

The city charges a building permit fee using a fee table based on project value. Plan review is a separate charge: 30% of the permit fee (minimum $78.00).

The fee table

Project valueFee
$1 – $100,000$101.00 + $12.04 per additional $1,000
$100,001 – $250,000$1,305.00 for the first $100,000 + $4.75 per additional $1,000
$250,001 – $500,000$2,017.00 for the first $250,000 + $4.50 per additional $1,000
$500,001 – $1,000,000$3,142.00 for the first $500,000 + $3.75 per additional $1,000
Over $1,000,000$5,017.00 for the first $1,000,000 + $3.00 per additional $1,000

Added to every matching permit

  • Zoning plan review (residential/multi-family new construction): 0.04% of project value, with a $15.00 minimum (Residential · new construction)
  • Zoning plan review (commercial new construction): 0.3% of project value, with a $25.00 minimum (Commercial · new construction)
  • Engineering plan review (residential/multi-family new construction): 0.1% of project value, with a $50.00 minimum (Residential · new construction)
  • Engineering plan review (commercial new construction): 0.4% of project value, with a $95.00 minimum (Commercial · new construction)
  • Fire plan review (multi-family/commercial): 0.3% of project value, with a $15.00 minimum (Commercial)
  • Certificate of occupancy: a flat $50.00 (new construction)

Surcharges

  • Inspector's Trust: 1.5% of the permit fee, minimum $2.00
  • Radon Tax: 1% of the permit fee, minimum $2.00
  • Technology Fee (BPI): 1.5% of the permit fee, minimum $1.50
  • Technology Fee (General Fund): 1.5% of the permit fee, minimum $1.50

What counts as project value

Your contract or bid price. Job valuation 'Includes all work including fair market value of design fees, site prep, labor, materials, sub-trades and mechanical trades, roofing, elevators, overhead and profit', excluding items needing a separate permit.

Worked example: a $350,000 new home

  1. Building permit fee: $2,017.00 for the first $250,000.00 + $4.50 × 100 per $1,000.00 over = $2,467.00
  2. Plan review fee: 30% of $2,467.00 = $740.10
  3. Zoning plan review (residential/multi-family new construction): 0.04% of $350,000.00 = $140.00
  4. Engineering plan review (residential/multi-family new construction): 0.1% of $350,000.00 = $350.00
  5. Certificate of occupancy: flat fee = $50.00
  6. Inspector's Trust: 1.5% of $2,467.00 = $37.01
  7. Radon Tax: 1% of $2,467.00 = $24.67
  8. Technology Fee (BPI): 1.5% of $2,467.00 = $37.01
  9. Technology Fee (General Fund): 1.5% of $2,467.00 = $37.01
  10. Total before trade permits: $3,882.80.

Fees people miss

May also apply (not in the totals above)

  • Zoning plan review (alterations other than interior-only renovation): when the alteration is not an interior renovation only (interior-only renovations pay $0); $75.00 on the standard projects.
  • Engineering plan review (alterations other than interior-only renovation): when the alteration is not an interior renovation only (interior-only renovations pay $0); $100.00 on the standard projects.
FeeAmount
Trade sub-permit fee (roofing, plumbing, mechanical, electrical)When: the project includes roofing, plumbing, mechanical or electrical work $25.00 each trade
Flood plan reviewWhen: property in a regulated flood zone $50.00 each
Flood inspectionWhen: property in a flood zone and staff require a flood inspection $58.00 each
Certificate of completionWhen: interior renovation (calculator logic) $50.00 each
Fire certificate of occupancyWhen: commercial with flood/new-construction conditions per calculator logic $110.00 each
Impact feesWhen: new development

How to apply

  1. Gather your plans and your project's total value.
  2. Submit to Building, Permitting & Inspections (BPI) online through EnerGov.
  3. Pay the permit and plan review fees when invoiced.
  4. Questions: 239-321-7925 · 1825 Hendry Street, Suite 101, Fort Myers

How Fort Myers compares

A $25,000 remodel costs $544.71 in Fort Myers: 43% above the national median of $380.00, and the 6th highest of 19 places we cover in Florida (state median $348.08).

A $350,000 new home costs $3,882.80 in Fort Myers: 33% above the national median of $2,918.63, and the 7th highest of 19 places we cover in Florida (state median $2,400.00).

Same standard projects everywhere, including plan review and required surcharges. All Florida places · Compare side by side

Fort Myers permit fee FAQ

How much is a building permit in Fort Myers, FL?

A $25,000 remodel: $544.71. A $350,000 new single-family: $3,882.80. These include every fee the schedule applies to that project; trade permits are separate.

Is plan review included in the Fort Myers permit fee?

No. Plan review is charged separately at 30% of the permit fee (minimum $78.00).

How does Fort Myers determine project value?

Your contract or bid price. Job valuation 'Includes all work including fair market value of design fees, site prep, labor, materials, sub-trades and mechanical trades, roofing, elevators, overhead and profit', excluding items needing a separate permit.

When did these Fort Myers fees take effect?

The schedule is effective Aug 5, 2025 (“Resolution 2025-96, effective 8/5/2025”). We last checked it against the official source on Nov 5, 2026.