Building Permit Fees in Grand Junction, CO (2026)

Grand Junction prices building permits with a fee table based on project value, with a $50.00 minimum, then charges plan review at 15% of the permit fee. Enter your project to see the exact math.

  • Official city schedule
  • Effective not stated
  • Verified Nov 5, 2026
Minimum fee
$50.00
Plan review
15%
$75k addition
$601

Permit fee calculator

Grand Junction schedule
Project type
Estimated permit fees $601.00
  1. 1. Building permit fee
    $475.70 for the first $50,000.00 + $5.00 × 25 per $1,000.00 over
    $601.00

May also apply (not in the total)

  • Work commencing before permit issuance
    When: work started before the permit was issued (at Building Official discretion)
    $601.00

Fees are estimates based on the official schedule linked below. Confirm with the permit office before applying. Separate electrical, plumbing, mechanical, fire, impact, utility and school fees are usually not included unless they are listed. BuildingPermitCost is not a government permit office, and this is not legal advice.

What common projects cost

Kitchen or bath remodel
$25,000 value, remodel 300 sq ft
$296.00
$296.00 building permit
Room addition
$75,000 value, addition 400 sq ft
$601.00
$601.00 building permit
New single-family home
$350,000 value, new single-family 2,400 sq ft
$1,701.00
$1,701.00 building permit

How Grand Junction calculates your permit fee

The city charges a building permit fee using a fee table based on project value, with a $50.00 minimum. Plan review is a separate charge: 15% of the permit fee. Electrical, plumbing and mechanical work gets its own permits.

The fee table

Project valueFee
$1 – $1,200$50.00
$1,201 – $2,000$50.00 for the first $1,200 + $2.20 per additional $100 or fraction
$2,001 – $25,000$68.00 for the first $2,000 + $9.90 per additional $1,000 or fraction
$25,001 – $50,000$295.70 for the first $25,000 + $7.20 per additional $1,000 or fraction
$50,001 – $100,000$475.70 for the first $50,000 + $5.00 per additional $1,000 or fraction
$100,001 – $500,000$725.70 for the first $100,000 + $3.90 per additional $1,000 or fraction
$500,001 – $1,000,000$2,285.70 for the first $500,000 + $3.30 per additional $1,000 or fraction
Over $1,000,000$3,935.70 for the first $1,000,000 + $2.20 per additional $1,000 or fraction

What counts as project value

Local valuation table. New construction and additions: 'select the applicable Square Foot Construction Cost multiplier in Table 3A ... The product of the identified multiplier and the area ... is the Total Valuation.' One- and two-family use the VB column (R-3 VB $74.68/sq ft; private garages use U Utility, VB $29.99). Remodels: 'actual labor and material cost of the project.' Table 3A values are from the 2003 IBC. The county page says valuations are rounded up in all cases.

Worked example: a $350,000 new home

  1. Building permit fee: $725.70 for the first $100,000.00 + $3.90 × 250 per $1,000.00 over = $1,701.00
  2. Total before trade permits: $1,701.00.

Fees people miss

May also apply (not in the totals above)

  • Work commencing before permit issuance: when work started before the permit was issued (at Building Official discretion); $296.00 on the standard projects.
FeeAmount
Residential submittal feeWhen: residential projects the Building Official judges at risk of non-issuance $250.00 maximum, credited to permit fee at issuance
Third-party plan review (department additional review)When: Building Department requires third-party plan review up to 20% of permit fee
Inspections outside normal business hoursWhen: after-hours inspection requested $60.00 per hour per person, 2-hour minimum
Inspections or plan review with no specific feeWhen: work not covered elsewhere $50.00 per hour per person
Re-inspectionWhen: failed or not-ready inspection $50.00 first re-inspection; $100 for additional re-inspection on same violation
Same-day inspectionWhen: same-day inspection requested $100.00 each, plus re-inspection fee
First reactivation of expired permitWhen: expired permit $50.00 each

Trade permits are separate. Electrical: Separate electrical, plumbing and mechanical permits use Table 2 on the actual cost of labor and materials. Plumbing: Table 2 on actual cost of labor and materials. Mechanical: Table 2 on actual cost of labor and materials.

How to apply

  1. Gather your plans and your project's total value.
  2. Submit to Mesa County Building Department (planning clearance from City of Grand Junction Community Development, 970-244-1430).
  3. Pay the permit and plan review fees when invoiced.
  4. Questions: 970-244-1631

How Grand Junction compares

A $25,000 remodel costs $296.00 in Grand Junction: 22% below the national median of $380.00, and the lowest of 15 places we cover in Colorado (state median $531.00).

A $75,000 addition costs $601.00 in Grand Junction: 27% below the national median of $820.58, and the 2nd lowest of 15 places we cover in Colorado (state median $1,174.21).

A $350,000 new home costs $1,701.00 in Grand Junction: 42% below the national median of $2,918.63, and the 2nd lowest of 15 places we cover in Colorado (state median $3,972.62).

Same standard projects everywhere, including plan review and required surcharges. All Colorado places · Compare side by side

Grand Junction permit fee FAQ

How much is a building permit in Grand Junction, CO?

A $25,000 remodel: $296.00. A $75,000 addition: $601.00. A $350,000 new single-family: $1,701.00. These include every fee the schedule applies to that project; trade permits are separate.

Is plan review included in the Grand Junction permit fee?

No. Plan review is charged separately at 15% of the permit fee.

How does Grand Junction determine project value?

Local valuation table. New construction and additions: 'select the applicable Square Foot Construction Cost multiplier in Table 3A ... The product of the identified multiplier and the area ... is the Total Valuation.' One- and two-family use the VB column (R-3 VB $74.68/sq ft; private garages use U Utility, VB $29.99). Remodels: 'actual labor and material cost of the project.' Table 3A values are from the 2003 IBC. The county page says valuations are rounded up in all cases.

Are electrical, plumbing and mechanical permits included?

No. They are separate permits. Electrical: Separate electrical, plumbing and mechanical permits use Table 2 on the actual cost of labor and materials. Plumbing: Table 2 on actual cost of labor and materials. Mechanical: Table 2 on actual cost of labor and materials.

When did these Grand Junction fees take effect?

The schedule does not state an effective date. We last checked it against the official source on Nov 5, 2026.