How Yuba City calculates your permit fee
The city charges a building permit fee using 3.3% of project value, with a $274.59 minimum. Plan review is a separate charge: 50% of the permit fee.
The fee table
Valuation multiplier tier 5,301 - 25,000
3.3% of project value, with a $274.59 minimum.
Valuation multiplier tier 25,001 - 50,000
2% of project value, with a $274.59 minimum.
Valuation multiplier tier 50,001 - 250,000
1% of project value, with a $274.59 minimum.
Valuation multiplier tier 250,001 - 500,000
0.9% of project value, with a $274.59 minimum.
Valuation multiplier tier 500,001 - 1,000,000
0.6% of project value, with a $274.59 minimum.
Valuation multiplier tier Over 1,000,000
0.7% of project value, with a $274.59 minimum.
Valuation $0-$5,300 (flat minimum fee)
A flat $274.59, with a $274.59 minimum.
Added to every matching permit
- Air quality fee (new residential): a flat $15.00 (Residential · new construction)
Surcharges
- SMIP seismic fee (residential): $0.13 per $1,000 of value, minimum $0.50
- SMIP seismic fee (commercial): $0.28 per $1,000 of value, minimum $0.50
- GIS/Technology fee: $0.95 per $1,000 of value, minimum $0.95
- Green building fee (CBSC): $0.04 per $1,000 of value
- Fire Department plan review: 24% of the plan review fee, minimum $214.00
What counts as project value
Local valuation table. Worksheet: 'Project Valuation (see Building Valuation Data sheet)'. The city's valuation data sheet was not read.
Worked example: a $350,000 new home
- Building permit fee: 0.9% of $350,000.00 = $3,150.00
- Plan review fee: 50% of $3,150.00 = $1,575.00
- Air quality fee (new residential): flat fee = $15.00
- SMIP seismic fee (residential): $350,000.00 ÷ 1,000 × $0.13 = $45.50
- GIS/Technology fee: $350,000.00 ÷ 1,000 × $0.95 = $332.50
- Green building fee (CBSC): $350,000.00 ÷ 1,000 × $0.04 = $14.00
- Total before trade permits: $5,132.00.
Fees people miss
May also apply (not in the totals above)
- GIS/Technology fee (remodel): when the GIS/Technology fee is charged on remodel (non-new-construction) permits; $23.75 on the standard projects.
- City business license fee: when a contractor pulls the permit (contractors only); $11.00 on the standard projects.
- Residential fire sprinkler fee: when the new home has a residential fire sprinkler system; $427.50 on the standard projects.
| Fee | Amount |
|---|---|
| Building admin fee (permit tech plan review / OTC review)When: permit tech or over-the-counter review is performed | $228.56 each |
| Re-inspection / special inspectionWhen: re-inspection or special inspection | $182.58 per hour (1 hour minimum) |
| After-hours inspectionWhen: after-hours inspection requested | $274.59 per hour (2 hour minimum) |
| Plan check after 3rd checkWhen: more than three plan checks | $182.58 per hour |
| Development impact fees (single family) | |
| Sewer connection (single family dwelling)When: new sewer connection | $7,227.53 each |
| Water connection 1-inch (25 GPM)When: new water connection | $9,573.12 each |
Will fees go up?
The schedule provides for a 2.4% adjustment each July 1 (Feb CPI). Schedule header: 'Feb 2026 CPI 2.4%' applied for July 1, 2026. Values stored as printed.
How to apply
- Gather your plans and your project's total value.
- Submit to Development Services Department - Building Division.
- Pay the permit and plan review fees when invoiced.
- Questions: (530) 822-4629 · 1201 Civic Center Blvd., Yuba City, CA 95993