How Fresno calculates your permit fee
The city charges a building permit fee using a fee table based on floor area. Plan review is a separate charge: its own fee table.
The fee table
Single-family/duplex, custom plan (R-3), inspection fee
| Floor area | Fee |
|---|---|
| 0 sq ft – 1,000 sq ft | $1,946.03 |
| 1,000 sq ft – 2,000 sq ft | $1,946.03 for the first 1,000 sq ft + $0.13 per additional sq ft or fraction |
| 2,000 sq ft – 3,000 sq ft | $2,079.71 for the first 2,000 sq ft + $0.37 per additional sq ft or fraction |
| 3,000 sq ft – 5,000 sq ft | $2,451.09 for the first 3,000 sq ft + $0.25 per additional sq ft or fraction |
| 5,000 sq ft – 7,500 sq ft | $2,941.31 for the first 5,000 sq ft + $0.42 per additional sq ft or fraction |
| Over 7,500 sq ft | $3,996.02 for the first 7,500 sq ft + $0.53 per additional sq ft or fraction |
Residential room addition, inspection fee
| Floor area | Fee |
|---|---|
| 0 sq ft – 167 sq ft | $884.55 |
| 167 sq ft – 333 sq ft | $884.55 for the first 167 sq ft + $0.37 per additional sq ft or fraction |
| 333 sq ft – 500 sq ft | $945.32 for the first 333 sq ft + $1.01 per additional sq ft or fraction |
| 500 sq ft – 833 sq ft | $1,114.12 for the first 500 sq ft + $0.67 per additional sq ft or fraction |
| 833 sq ft – 1,250 sq ft | $1,336.96 for the first 833 sq ft + $1.15 per additional sq ft or fraction |
| Over 1,250 sq ft | $1,816.37 for the first 1,250 sq ft + $1.45 per additional sq ft or fraction |
Residential remodel, inspection fee
| Floor area | Fee |
|---|---|
| 0 sq ft – 500 sq ft | $489.83 |
| Over 500 sq ft | $489.83 for the first 500 sq ft + $207.96 per additional 500 sq ft or fraction |
Surcharges
- General Plan and Related Document Update and Maintenance surcharge: 12.83% of the permit fee
- Technology - Entitlement Processing System Update surcharge: $23.79
- California Building Standards Commission (SB 1473) surcharge: $1.00 per $25,000 of value
What counts as project value
Floor area (square feet). New construction, additions and major remodels are priced by floor area from occupancy-specific tables (base cost at each square-foot threshold plus a cost per sq ft between thresholds), with separate plan check and inspection tables. Mechanical, plumbing, electrical and energy plan check for these projects are included. Valuation is used only for the state CBSC surcharge.
Worked example: a $350,000 new home
- Building permit fee: $2,079.71 for the first 2,000 sq ft + $0.37 × 400 per sq ft over = $2,228.91
- Plan review fee: $667.70 for the first 2,000 sq ft + $0.20 × 400 per sq ft over = $748.90
- General Plan and Related Document Update and Maintenance surcharge: 12.83% of $2,228.91 = $285.97
- Technology - Entitlement Processing System Update surcharge: fixed = $23.79
- California Building Standards Commission (SB 1473) surcharge: $1.00 × 14 per $25,000.00 = $14.00
- Total before trade permits: $3,301.57.
Fees people miss
May also apply (not in the totals above)
- Working without required permit: when work without permit; $1,959.32 on the standard projects.
| Fee | Amount |
|---|---|
| Blended hourly rate (services not listed / beyond regular effort)When: services not listed | $149.07 per hour |
| Addendum to approved building plansWhen: plan addenda | hourly, 1-hour minimum |
| Building permit renewal of expired permitWhen: expired permit | 25% of permit fee, minimum shown in schedule |
| Strong-Motion Instrumentation and Seismic Hazard Mapping fee | set by California Dept. of Conservation |
| County Facilities Impact Fee | per County ordinance, paid to County |
How to apply
- Gather your plans and your project's total value and floor area.
- Submit to City of Fresno Planning & Development Department, Building & Safety Services through Accela Citizen Access.
- Pay the permit and plan review fees when invoiced.