How Stanislaus County calculates your permit fee
The county charges a building permit fee using a fee table based on project value, plus a $57.50 application fee, with a $160.40 minimum. Plan review is a separate charge: 65% of the permit fee. Electrical, plumbing and mechanical work gets its own permits.
The fee table
| Project value | Fee |
|---|---|
| $1 – $500 | $160.40 |
| $501 – $2,000 | $160.40 for the first $500 + $3.78 per additional $100 or fraction |
| $2,001 – $25,000 | $217.10 for the first $2,000 + $12.33 per additional $1,000 or fraction |
| $25,001 – $50,000 | $500.59 for the first $25,000 + $12.95 per additional $1,000 or fraction |
| $50,001 – $100,000 | $824.34 for the first $50,000 + $8.99 per additional $1,000 or fraction |
| $100,001 – $500,000 | $1,273.84 for the first $100,000 + $7.19 per additional $1,000 or fraction |
| $500,001 – $1,000,000 | $4,149.84 for the first $500,000 + $6.09 per additional $1,000 or fraction |
| Over $1,000,000 | $7,194.00 for the first $1,000,000 + $3.99 per additional $1,000 or fraction |
Plus an application fee of $57.50.
Surcharges
- General Plan Maintenance Fee: $1.28 per $1,000 of value
- State SMIP (Strong Motion), Group R 1-3 stories: $0.13 per $1,000 of value, minimum $0.50
- State SMIP (Strong Motion), all other buildings: $0.28 per $1,000 of value, minimum $0.50
- State Building Standards Administration Special Revolving Fund (CBSC): $0.04 per $1,000 of value, minimum $1.00
What counts as project value
ICC Building Valuation Data table. The Building Official determines valuation: total value of all construction work incl. finish work, roofing, electrical, plumbing, HVAC and permanent equipment, using the August 2020 ICC Building Valuation Data (Building Safety Journal).
Worked example: a $350,000 new home
- Building permit fee: $1,273.84 for the first $100,000.00 + $7.19 × 250 per $1,000.00 over = $3,071.34
- Application fee: fixed = $57.50
- Plan review fee: 65% of $3,071.34 = $1,996.37
- General Plan Maintenance Fee: $350,000.00 ÷ 1,000 × $1.28 = $448.00
- State SMIP (Strong Motion), Group R 1-3 stories: $350,000.00 ÷ 1,000 × $0.13 = $45.50
- State Building Standards Administration Special Revolving Fund (CBSC): $350,000.00 ÷ 1,000 × $0.04 = $14.00
- Total before trade permits: $5,632.71.
Fees people miss
May also apply (not in the totals above)
- One-stop-shop payment collection fee: when Building Permit Services collects fees for other County departments, fire districts or the State HCD; $8.50 on the standard projects.
- Credit card transaction fee: when paying by credit card; $32.20 on the standard projects.
| Fee | Amount |
|---|---|
| Additional plan review for incomplete or changed plans (1/2 hour minimum)When: incomplete or changed plans | $142.25 per hour |
| Field inspection hourly rateWhen: hourly-billed inspections | $126.25 per hour |
| After hours / weekend inspection (3 hour minimum $565.50)When: after hours inspection requested | $188.75 per hour |
| Investigation fee (work started without permit)When: work commenced without a permit | equal to permit fee |
| County Public Facilities Fees, school district and fire district fees | separate schedules |
Trade permits are separate. Electrical: Field inspection minimum $95.00 (2026) plus per-device and service charges; not fully extracted. Plumbing: Field inspection minimum plus per-fixture charge; not fully extracted. Mechanical: Field inspection minimum plus per-equipment charge; not fully extracted.
How to apply
- Gather your plans and your project's total value.
- Submit to Planning and Community Development, Building Permit Division.
- Pay the permit and plan review fees when invoiced.