Building Permit Fees in Pleasanton, CA (2026)

Pleasanton prices building permits with a fee table based on project value, with a $120.00 minimum, then charges plan review at 75% of the permit fee (minimum $180.00). Enter your project to see the exact math.

  • Official city schedule
  • Effective Jan 1, 2026
  • Verified Nov 5, 2026
Minimum fee
$120.00
Plan review
75%
$75k addition
$2,078

Permit fee calculator

Pleasanton schedule, eff. Jan 1, 2026
Project type
Estimated permit fees $2,078.26
  1. 1. Building permit fee
    $905.00 for the first $50,000.00 + $9.70 × 25 per $1,000.00 over
    $1,147.50
  2. 2. Plan review fee
    75% of $1,147.50
    $860.63
  3. 3. Technology fee
    5% of $1,147.50
    $57.38
  4. 4. SMIP (Strong Motion Instrumentation Program), residential
    $75,000.00 ÷ 1,000 × $0.13
    $9.75
  5. 5. CBSC Special Revolving Fund
    $1.00 × 3 per $25,000.00
    $3.00

May also apply (not in the total)

  • Sub-trades surcharge
    When: the project includes multi-trade (electrical, plumbing and/or mechanical) work with the building permit
    $286.88
  • Energy surcharge
    When: the project must comply with the California Energy Code (Title 24, Part 6)
    $286.88
  • Accessibility surcharge
    When: the project requires State accessibility, FHAA or ADA compliance
    $172.13
  • Green building surcharge
    When: the permit requires CALGreen compliance
    $172.13
  • Stormwater surcharge
    When: the project requires SWPPP or on-site stormwater treatment
    $172.13
  • Waste Management Plan fee
    When: a Waste Management Plan is required and the Green Building Surcharge does not apply
    $150.00

Fees are estimates based on the official schedule linked below. Confirm with the permit office before applying. Separate electrical, plumbing, mechanical, fire, impact, utility and school fees are usually not included unless they are listed. BuildingPermitCost is not a government permit office, and this is not legal advice.

What common projects cost

Kitchen or bath remodel
$25,000 value, remodel 300 sq ft
$994.37
$550.07 building permit + $412.55 plan review + $27.50 technology + $3.25 smip (strong motion instrumentation program), residential + $1.00 cbsc special revolving fund
Room addition
$75,000 value, addition 400 sq ft
$2,078.26
$1,147.50 building permit + $860.63 plan review + $57.38 technology + $9.75 smip (strong motion instrumentation program), residential + $3.00 cbsc special revolving fund
New single-family home
$350,000 value, new single-family 2,400 sq ft
$6,143.50
$3,380.00 building permit + $2,535.00 plan review + $169.00 technology + $45.50 smip (strong motion instrumentation program), residential + $14.00 cbsc special revolving fund

How Pleasanton calculates your permit fee

The city charges a building permit fee using a fee table based on project value, with a $120.00 minimum. Plan review is a separate charge: 75% of the permit fee (minimum $180.00). Electrical, plumbing and mechanical work gets its own permits.

The fee table

Project valueFee
$1 – $1,000$120.00
$1,001 – $2,000$145.00
$2,001 – $25,000$180.00 for the first $2,000 + $16.09 per additional $1,000 or fraction
$25,001 – $50,000$560.00 for the first $25,000 + $13.80 per additional $1,000 or fraction
$50,001 – $100,000$905.00 for the first $50,000 + $9.70 per additional $1,000 or fraction
$100,001 – $500,000$1,395.00 for the first $100,000 + $7.94 per additional $1,000 or fraction
$500,001 – $1,000,000$4,605.00 for the first $500,000 + $6.34 per additional $1,000 or fraction
Over $1,000,000$7,815.00 for the first $1,000,000 + $5.52 per additional $1,000 or fraction

Surcharges

  • Technology fee: 5% of the permit fee
  • SMIP (Strong Motion Instrumentation Program), residential: $0.13 per $1,000 of value, minimum $0.50
  • CBSC Special Revolving Fund: $1.00 per $25,000 of value
  • SMIP (Strong Motion Instrumentation Program), non-residential: $0.28 per $1,000 of value, minimum $0.50

What counts as project value

Local valuation table. 'New Construction and Addition valuations are usually based on square footage using our New Construction Valuation Table, see page 5', but page 5 of the posted PDF has no valuation table (checked 2026-11-05) and the city's per-sq-ft rates are not published there. The calculator therefore uses the valuation the user enters; for new construction and additions the city's own table value may differ. Repairs, remodels and TIs use the applicant's construction cost or the Building Official's determination.

Worked example: a $350,000 new home

  1. Building permit fee: $1,395.00 for the first $100,000.00 + $7.94 × 250 per $1,000.00 over = $3,380.00
  2. Plan review fee: 75% of $3,380.00 = $2,535.00
  3. Technology fee: 5% of $3,380.00 = $169.00
  4. SMIP (Strong Motion Instrumentation Program), residential: $350,000.00 ÷ 1,000 × $0.13 = $45.50
  5. CBSC Special Revolving Fund: $1.00 × 14 per $25,000.00 = $14.00
  6. Total before trade permits: $6,143.50.

Fees people miss

May also apply (not in the totals above)

  • Sub-trades surcharge: when the project includes multi-trade (electrical, plumbing and/or mechanical) work with the building permit; $137.52 on the standard projects.
  • Energy surcharge: when the project must comply with the California Energy Code (Title 24, Part 6); $137.52 on the standard projects.
  • Accessibility surcharge: when the project requires State accessibility, FHAA or ADA compliance; $82.51 on the standard projects.
  • Green building surcharge: when the permit requires CALGreen compliance; $82.51 on the standard projects.
  • Stormwater surcharge: when the project requires SWPPP or on-site stormwater treatment; $82.51 on the standard projects.
  • Waste Management Plan fee: when a Waste Management Plan is required and the Green Building Surcharge does not apply; $150.00 on the standard projects.
FeeAmount
Investigation fee (work without permit)When: work commenced before permits obtained 100% of building permit fees
Expedited plan reviewWhen: applicant requests expedited review and staff is available additional 50% of plan review fees
Hourly inspection rate (re-inspections, after hours)When: re-inspection or special inspection $165.00 per hour
Credit/debit card convenience feeWhen: paid by card 2.5%
Development feesWhen: new buildings, additions or change of use creating traffic/sewer impact see Development Fees handout
School impact feesWhen: additions and new construction over 500 sq ft set by Pleasanton Unified School District

Trade permits are separate. Electrical: Residential electrical permit not itemized, with an associated building permit: $120. Itemized commercial fees per 1,000 sq ft. Mechanical: Residential mechanical permit not in conjunction with a building permit: $120. Plumbing: Residential plumbing permit not in conjunction with a building permit: $120.

How to apply

  1. Gather your plans and your project's total value.
  2. Submit to Building and Safety Division, Community and Economic Development online through Accela Citizen Access (ACA).
  3. Pay the permit and plan review fees when invoiced.
  4. Questions: 925-931-5300 · 200 Old Bernal Avenue, Pleasanton, CA 94566

How Pleasanton compares

A $25,000 remodel costs $994.37 in Pleasanton: about 2.6 times the national median of $380.00, and the 14th lowest of 43 places we cover in California (state median $1,263.01).

A $75,000 addition costs $2,078.26 in Pleasanton: about 2.5 times the national median of $820.58, and the 18th lowest of 45 places we cover in California (state median $2,473.00).

A $350,000 new home costs $6,143.50 in Pleasanton: about 2.1 times the national median of $2,918.63, and the 17th lowest of 47 places we cover in California (state median $6,927.50).

Same standard projects everywhere, including plan review and required surcharges. All California places · Compare side by side

Pleasanton permit fee FAQ

How much is a building permit in Pleasanton, CA?

A $25,000 remodel: $994.37. A $75,000 addition: $2,078.26. A $350,000 new single-family: $6,143.50. These include every fee the schedule applies to that project; trade permits are separate.

Is plan review included in the Pleasanton permit fee?

No. Plan review is charged separately at 75% of the permit fee (minimum $180.00).

How does Pleasanton determine project value?

Local valuation table. 'New Construction and Addition valuations are usually based on square footage using our New Construction Valuation Table, see page 5', but page 5 of the posted PDF has no valuation table (checked 2026-11-05) and the city's per-sq-ft rates are not published there. The calculator therefore uses the valuation the user enters; for new construction and additions the city's own table value may differ. Repairs, remodels and TIs use the applicant's construction cost or the Building Official's determination.

Are electrical, plumbing and mechanical permits included?

No. They are separate permits. Electrical: Residential electrical permit not itemized, with an associated building permit: $120. Itemized commercial fees per 1,000 sq ft. Mechanical: Residential mechanical permit not in conjunction with a building permit: $120. Plumbing: Residential plumbing permit not in conjunction with a building permit: $120.

When did these Pleasanton fees take effect?

The schedule is effective Jan 1, 2026 (“Building Permit and Plan Review Fees, January 1, 2026 (revised Jan. 1, 2026)”). We last checked it against the official source on Nov 5, 2026.