Building Permit Fees in Conroe, TX (2026)

Conroe prices building permits with $0.64 per square foot, then charges plan review at $0.32 per square foot. Enter your project to see the exact math.

  • Official city schedule
  • Effective Nov 13, 2025
  • Verified Nov 5, 2026
Minimum fee
—
Plan review
Separate
$75k addition
$384

Permit fee calculator

Conroe schedule, eff. Nov 13, 2025
Project type
Estimated permit fees $384.00
  1. 1. Building permit fee
    400 sq ft × $0.64
    $256.00
  2. 2. Plan review fee
    400 sq ft × $0.32
    $128.00

Fees are estimates based on the official schedule linked below. Confirm with the permit office before applying. Separate electrical, plumbing, mechanical, fire, impact, utility and school fees are usually not included unless they are listed. BuildingPermitCost is not a government permit office, and this is not legal advice.

What common projects cost

Kitchen or bath remodel
$25,000 value, remodel 300 sq ft
$288.00
$192.00 building permit + $96.00 plan review
Room addition
$75,000 value, addition 400 sq ft
$384.00
$256.00 building permit + $128.00 plan review
New single-family home
$350,000 value, new single-family 2,400 sq ft
$2,304.00
$1,536.00 building permit + $768.00 plan review

How Conroe calculates your permit fee

The city charges a building permit fee using $0.64 per square foot. Plan review is a separate charge: $0.32 per square foot. Electrical, plumbing and mechanical work gets its own permits.

The fee table

Residential dwellings (total sq ft of building area or work area)

$0.64 per square foot.

Commercial new construction and additions (multiplier 1.0)

Project valueFee
$1 – $500$50.00
$501 – $1,000$50.00 for the first $500 + $3.50 per additional $100 or fraction
$1,001 – $25,000$67.50 for the first $1,000 + $14.00 per additional $1,000 or fraction
$25,001 – $50,000$403.50 for the first $25,000 + $10.10 per additional $1,000 or fraction
$50,001 – $100,000$656.00 for the first $50,000 + $7.00 per additional $1,000 or fraction
$100,001 – $500,000$1,006.00 for the first $100,000 + $5.00 per additional $1,000 or fraction
$500,001 – $1,000,000$3,006.00 for the first $500,000 + $4.75 per additional $1,000 or fraction
Over $1,000,000$5,381.00 for the first $1,000,000 + $3.15 per additional $1,000 or fraction

What counts as project value

Floor area (square feet). Residential dwelling permits are priced per square foot of building area or work area. Commercial new construction/additions (and residential structures that are not dwellings) use valuation from the most recent ICC Building Valuation Data table (or as determined by the building official) times work area, then the valuation fee table times a multiplier. Alterations/remodels/interior build-outs use project valuation or as determined by the building official.

Worked example: a $350,000 new home

  1. Building permit fee: 2,400 sq ft × $0.64 = $1,536.00
  2. Plan review fee: 2,400 sq ft × $0.32 = $768.00
  3. Total before trade permits: $2,304.00.

Fees people miss

FeeAmount
Additional plan review, 4th submittal and laterWhen: more than three plan submittals 4th: additional 50% of permit fee; 5th: double plan review fee; 6th+: triple
Inspection for certificate of occupancy, change of ownership or business nameWhen: change of ownership or business name $200.00 each
Temporary certificate of occupancyWhen: temporary CO requested $250.00 each
Replacement / lost certificate of occupancyWhen: replacement requested $20.00 each
Investigation fee (work started prior to permit)When: work started before permit $2,000.00 or double permit fee, whichever is greater
Permit reinstatement (unlicensed contractors)When: unlicensed contractor $2,000.00 each
Demolition without a building permitWhen: demolition without a building permit $150.00 each
ReinspectionWhen: failed inspection $75.00 1st; 2nd $100; 3rd $150; 4th+ $300
After hours inspectionWhen: after-hours inspection $300.00 each
Swimming pool depositWhen: swimming pool permit $500.00 deposit

Trade permits are separate. Electrical: Permit = $75 base fee + required inspections by work-area size (underground, rough-in, TCI, final): $15 each up to 1,000 sq ft, $50 up to 5,000, $100 up to 10,000, $150 up to 50,000, $200 over 50,000. Service/meter loop replacement $100-$350 by amperage. Plumbing: Permit = $75 base fee + inspections by work-area size (underground, top out, final): $15 each up to 1,000 sq ft, $50 up to 5,000, $100 up to 10,000, $150 up to 50,000, $200 over 50,000. Mechanical: $75 base fee; residential partial/full change-out or new system/new construction $25; commercial 1-3 tons $50 plus $12.50 per ton over 3. Fuel gas: $75 base + inspections by area as for plumbing.

How to apply

  1. Gather your plans and your project's total value and floor area.
  2. Submit to City of Conroe Building Inspections & Permits through OpenGov Applicant Portal.
  3. Pay the permit and plan review fees when invoiced.

How Conroe compares

A $25,000 remodel costs $288.00 in Conroe: 24% below the national median of $380.00, and the 4th highest of 19 places we cover in Texas (state median $201.75).

A $75,000 addition costs $384.00 in Conroe: 53% below the national median of $820.58, and the 2nd highest of 17 places we cover in Texas (state median $264.82).

A $350,000 new home costs $2,304.00 in Conroe: 21% below the national median of $2,918.63, and the 3rd highest of 20 places we cover in Texas (state median $1,448.00).

Same standard projects everywhere, including plan review and required surcharges. All Texas places · Compare side by side

Conroe permit fee FAQ

How much is a building permit in Conroe, TX?

A $25,000 remodel: $288.00. A $75,000 addition: $384.00. A $350,000 new single-family: $2,304.00. These include every fee the schedule applies to that project; trade permits are separate.

Is plan review included in the Conroe permit fee?

No. Plan review is charged separately at $0.32 per square foot.

How does Conroe determine project value?

Floor area (square feet). Residential dwelling permits are priced per square foot of building area or work area. Commercial new construction/additions (and residential structures that are not dwellings) use valuation from the most recent ICC Building Valuation Data table (or as determined by the building official) times work area, then the valuation fee table times a multiplier. Alterations/remodels/interior build-outs use project valuation or as determined by the building official.

Are electrical, plumbing and mechanical permits included?

No. They are separate permits. Electrical: Permit = $75 base fee + required inspections by work-area size (underground, rough-in, TCI, final): $15 each up to 1,000 sq ft, $50 up to 5,000, $100 up to 10,000, $150 up to 50,000, $200 over 50,000. Service/meter loop replacement $100-$350 by amperage. Plumbing: Permit = $75 base fee + inspections by work-area size (underground, top out, final): $15 each up to 1,000 sq ft, $50 up to 5,000, $100 up to 10,000, $150 up to 50,000, $200 over 50,000. Mechanical: $75 base fee; residential partial/full change-out or new system/new construction $25; commercial 1-3 tons $50 plus $12.50 per ton over 3. Fuel gas: $75 base + inspections by area as for plumbing.

When did these Conroe fees take effect?

The schedule is effective Nov 13, 2025 (“Ordinance No. 2756-25, passed November 13, 2025, effective immediately upon adoption”). We last checked it against the official source on Nov 5, 2026.