Building Permit Fees in Washoe County, NV (2026)

Washoe County prices building permits with a fee table based on project value, with a $45.00 minimum, then charges plan review at 50% of the permit fee. Enter your project to see the exact math.

  • Official county schedule
  • Effective not stated
  • Verified Nov 5, 2026
Minimum fee
$45.00
Plan review
50%
$75k addition
$1,360

Permit fee calculator

Washoe County schedule
Project type
Estimated permit fees $1,360.31
  1. 1. Building permit fee
    $716.12 for the first $50,000.00 + $7.63 × 25 per $1,000.00 over
    $906.87
  2. 2. Plan review fee
    50% of $906.87
    $453.44

May also apply (not in the total)

  • Park Tax (NRS 278.4983)
    When: new residential dwelling unit on an undeveloped lot ($1,000 cap is per dwelling unit)
    $750.00

Fees are estimates based on the official schedule linked below. Confirm with the permit office before applying. Separate electrical, plumbing, mechanical, fire, impact, utility and school fees are usually not included unless they are listed. BuildingPermitCost is not a government permit office, and this is not legal advice.

What common projects cost

Kitchen or bath remodel
$25,000 value, remodel 300 sq ft
$665.43
$443.62 building permit + $221.81 plan review
Room addition
$75,000 value, addition 400 sq ft
$1,360.31
$906.87 building permit + $453.44 plan review
New single-family home
$350,000 value, new single-family 2,400 sq ft
$3,870.18
$2,580.12 building permit + $1,290.06 plan review

How Washoe County calculates your permit fee

The county charges a building permit fee using a fee table based on project value, with a $45.00 minimum. Plan review is a separate charge: 50% of the permit fee. Electrical, plumbing and mechanical work gets its own permits.

The fee table

Project valueFee
$1 – $500$45.00
$501 – $2,000$45.00 for the first $500 + $3.36 per additional $100 or fraction
$2,001 – $25,000$95.40 for the first $2,000 + $15.14 per additional $1,000 or fraction
$25,001 – $50,000$443.62 for the first $25,000 + $10.90 per additional $1,000 or fraction
$50,001 – $100,000$716.12 for the first $50,000 + $7.63 per additional $1,000 or fraction
$100,001 – $500,000$1,097.62 for the first $100,000 + $5.93 per additional $1,000 or fraction
$500,001 – $1,000,000$3,469.62 for the first $500,000 + $5.07 per additional $1,000 or fraction
$1,000,001 – $10,000,000$6,004.62 for the first $1,000,000 + $3.36 per additional $1,000 or fraction
Over $10,000,000$36,244.62 for the first $10,000,000 + $2.36 per additional $1,000 or fraction

What counts as project value

Local valuation table. The county calculates project value from its Building Construction Costs per Square Foot table (group x construction type). New single-family dwellings and additions are R-3; R-3 type VB = $94.99/sq ft. Private garages, residential remodels and sunrooms use Utility, miscellaneous (U, VB = $36.91/sq ft). Unfinished basements $25.00/sf. Decks $15/sf, carport/patio cover $20/sf. Incline Village area add 15 percent. If not defined, the applicant provides an estimated value (materials and labor); final valuation set by the Building Official. The calculator applies Table 1 to the entered valuation.

Worked example: a $350,000 new home

  1. Building permit fee: $1,097.62 for the first $100,000.00 + $5.93 × 250 per $1,000.00 over = $2,580.12
  2. Plan review fee: 50% of $2,580.12 = $1,290.06
  3. Total before trade permits: $3,870.18.

Fees people miss

May also apply (not in the totals above)

  • Park Tax (NRS 278.4983): when new residential dwelling unit on an undeveloped lot ($1,000 cap is per dwelling unit); $250.00 on the standard projects.
FeeAmount
Regional Road Impact Fee (RTC)When: new development generating trips (new dwellings, commercial)
Building permit renewalWhen: permit renewal $45.00 plus 10% of original building permit fee and sub fees
Inspection outside normal business hoursWhen: after-hours inspection $135.00 per hour (2 hour minimum)
Additional inspection (Article 109)When: additional inspection $90.00 per hour (1 hour minimum)
Inspections with no specific feeWhen: inspection not otherwise priced $45.00 per hour (1 hour minimum)
Additional plan review for changes/revisionsWhen: plan changes, revisions or deferred submittals $90.00 per hour (half hour minimum)
Business license inspectionWhen: business license $50.00 each
Mobile home review and site inspectionWhen: mobile home $100.00 each
Move or alterWhen: move or alter a building $100.00 each

Trade permits are separate. Mechanical: Table 4: $45 permit issuance fee plus unit fees (e.g. furnace up to 100,000 Btu/h $20, appliance vent $7). Plumbing: Table 5: $45 permit issuance fee plus unit fees (e.g. each fixture $6, water heater $8). Electrical: Table 8: $45 permit issuance fee; new single- and two-family residential buildings $0.04 per sq ft (excluding garages); other residential/alterations $0.03 per sq ft.

How to apply

  1. Gather your plans and your project's total value.
  2. Submit to Washoe County Building Program (Community Services Department) online through One Regional portal (OneNV).
  3. Pay the permit and plan review fees when invoiced.
  4. Questions: 775-328-2003 · 1001 E. Ninth Street, Reno, NV 89512

How Washoe County compares

A $25,000 remodel costs $665.43 in Washoe County: 75% above the national median of $380.00.

A $75,000 addition costs $1,360.31 in Washoe County: 66% above the national median of $820.58.

A $350,000 new home costs $3,870.18 in Washoe County: 33% above the national median of $2,918.63.

Cities in Washoe County with their own fee schedule on this site: Reno. Inside those cities, check whether the city or the county issues your permit.

Same standard projects everywhere, including plan review and required surcharges. All Nevada places · Compare side by side

Washoe County permit fee FAQ

How much is a building permit in Washoe County, NV?

A $25,000 remodel: $665.43. A $75,000 addition: $1,360.31. A $350,000 new single-family: $3,870.18. These include every fee the schedule applies to that project; trade permits are separate.

Is plan review included in the Washoe County permit fee?

No. Plan review is charged separately at 50% of the permit fee.

How does Washoe County determine project value?

Local valuation table. The county calculates project value from its Building Construction Costs per Square Foot table (group x construction type). New single-family dwellings and additions are R-3; R-3 type VB = $94.99/sq ft. Private garages, residential remodels and sunrooms use Utility, miscellaneous (U, VB = $36.91/sq ft). Unfinished basements $25.00/sf. Decks $15/sf, carport/patio cover $20/sf. Incline Village area add 15 percent. If not defined, the applicant provides an estimated value (materials and labor); final valuation set by the Building Official. The calculator applies Table 1 to the entered valuation.

Are electrical, plumbing and mechanical permits included?

No. They are separate permits. Mechanical: Table 4: $45 permit issuance fee plus unit fees (e.g. furnace up to 100,000 Btu/h $20, appliance vent $7). Plumbing: Table 5: $45 permit issuance fee plus unit fees (e.g. each fixture $6, water heater $8). Electrical: Table 8: $45 permit issuance fee; new single- and two-family residential buildings $0.04 per sq ft (excluding garages); other residential/alterations $0.03 per sq ft.

When did these Washoe County fees take effect?

The schedule does not state an effective date. We last checked it against the official source on Nov 5, 2026.