BuildingPermitCost

Building Permit Fees in Reno, NV (2026)

Reno prices building permits with a fee table based on project value, plus a $45.00 application fee, with a $26.80 minimum, then charges plan review at 65% of the permit fee. Enter your project to see the exact math.

  • Official city schedule
  • Effective Jul 1, 2026
  • Verified Nov 4, 2026
Minimum fee
$26.80
Plan review
65%
$75k addition
$1,638

Permit fee calculator

Reno schedule, eff. Jul 1, 2026
Project type
Estimated permit fees $1,637.78
  1. 1. Building permit fee
    $736.80 for the first $50,000.00 + $8.05 × 25 per $1,000.00 over
    $938.05
  2. 2. Application fee
    fixed
    $45.00
  3. 3. Plan review fee
    65% of $938.05
    $609.73
  4. 4. Permit issuance fee
    fixed
    $45.00

Fees are estimates based on the official schedule linked below. Confirm with the permit office before applying. Separate electrical, plumbing, mechanical, fire, impact, utility and school fees are usually not included unless they are listed. BuildingPermitCost is not a government permit office, and this is not legal advice.

What common projects cost

Kitchen or bath remodel
$25,000 value, remodel 300 sq ft
$829.28
$448.05 building permit + $45.00 application + $291.23 plan review + $45.00 permit issuance
Room addition
$75,000 value, addition 400 sq ft
$1,637.78
$938.05 building permit + $45.00 application + $609.73 plan review + $45.00 permit issuance
New single-family home
$350,000 value, new single-family 2,400 sq ft
$4,527.35
$2,689.30 building permit + $45.00 application + $1,748.05 plan review + $45.00 permit issuance

How Reno calculates your permit fee

The city charges a building permit fee using a fee table based on project value, plus a $45.00 application fee, with a $26.80 minimum. Plan review is a separate charge: 65% of the permit fee.

The fee table

Project valueFee
$1 – $500$26.80
$501 – $2,000$26.80 for the first $500 + $3.55 per additional $100 or fraction
$2,001 – $25,000$80.05 for the first $2,000 + $16.00 per additional $1,000 or fraction
$25,001 – $50,000$448.05 for the first $25,000 + $11.55 per additional $1,000 or fraction
$50,001 – $100,000$736.80 for the first $50,000 + $8.05 per additional $1,000 or fraction
$100,001 – $500,000$1,139.30 for the first $100,000 + $6.20 per additional $1,000 or fraction
$500,001 – $1,000,000$3,619.30 for the first $500,000 + $5.50 per additional $1,000 or fraction
Over $1,000,000$6,369.30 for the first $1,000,000 + $3.75 per additional $1,000 or fraction

Plus an application fee of $45.00.

Surcharges

  • Permit issuance fee: $45.00

What counts as project value

Not stated in the schedule. Valuation-based permits (residential and commercial new construction, remodel, addition and any permit not listed as EZ or flat rate) use the Permit Fee Table. The fee schedule does not say how valuation is determined.

Worked example: a $350,000 new home

  1. Building permit fee: $1,139.30 for the first $100,000.00 + $6.20 × 250 per $1,000.00 over = $2,689.30
  2. Application fee: fixed = $45.00
  3. Plan review fee: 65% of $2,689.30 = $1,748.05
  4. Permit issuance fee: fixed = $45.00
  5. Total before trade permits: $4,527.35.

Fees people miss

FeeAmount
FEMA elevation certificate reviewWhen: when applicable (flood zone) $130.00 each
Sewer fixture count fee (commercial)When: commercial, when applicable $137.00 each
Supplemental plan review/inspection (permit revisions)When: permit revisions $270.00 each
Plan review/inspection hourly (building, engineering, planning, fire)When: hourly services $135.00 per hour
Temporary certificate of occupancyWhen: temporary CO requested $1,125.00 each
After hours call-out (scheduled)When: after hours $270.00 each
Incomplete plan submissionWhen: incomplete submittal $135.00 each
Other agency/impact feesWhen: based on scope of work varies

How to apply

  1. Gather your plans and your project's total value.
  2. Submit to City of Reno Development Services, Building and Safety.
  3. Pay the permit and plan review fees when invoiced.
  4. Questions: 775-334-2063

How Reno compares

A $25,000 remodel costs $829.28 in Reno: about 2.2 times the national median of $380.00.

A $75,000 addition costs $1,637.78 in Reno: about twice the national median of $820.58.

A $350,000 new home costs $4,527.35 in Reno: 55% above the national median of $2,918.63.

Same standard projects everywhere, including plan review and required surcharges. All Nevada places · Compare side by side

Reno permit fee FAQ

How much is a building permit in Reno, NV?

A $25,000 remodel: $829.28. A $75,000 addition: $1,637.78. A $350,000 new single-family: $4,527.35. These include every fee the schedule applies to that project; trade permits are separate.

Is plan review included in the Reno permit fee?

No. Plan review is charged separately at 65% of the permit fee.

How does Reno determine project value?

Not stated in the schedule. Valuation-based permits (residential and commercial new construction, remodel, addition and any permit not listed as EZ or flat rate) use the Permit Fee Table. The fee schedule does not say how valuation is determined.

When did these Reno fees take effect?

The schedule is effective Jul 1, 2026 (“Fees Effective July 1, 2026 (FY27)”). We last checked it against the official source on Nov 4, 2026.