Building Permit Fees in Rochester, MN (2026)

Rochester prices building permits with a fee table based on project value, with a $25.00 minimum, then charges plan review at 65% of the permit fee. Enter your project to see the exact math.

  • Official city schedule
  • Effective not stated
  • Verified Nov 5, 2026
Minimum fee
$25.00
Plan review
65%
$75k addition
$886

Permit fee calculator

Rochester schedule
Project type
Estimated permit fees $886.05
  1. 1. Building permit fee
    $424.50 for the first $50,000.00 + $4.50 × 25 per $1,000.00 over
    $537.00
  2. 2. Plan review fee
    65% of $537.00
    $349.05

May also apply (not in the total)

  • Zoning certificate fee (residential uses)
    When: a zoning certificate is required for the improvement (Planning and Zoning Division)
    $225.96
  • Administrative fee
    When: the $90 administrative fee listed in the building permit section applies to the permit
    $90.00

Fees are estimates based on the official schedule linked below. Confirm with the permit office before applying. Separate electrical, plumbing, mechanical, fire, impact, utility and school fees are usually not included unless they are listed. BuildingPermitCost is not a government permit office, and this is not legal advice.

What common projects cost

Kitchen or bath remodel
$25,000 value, remodel 300 sq ft
$432.30
$262.00 building permit + $170.30 plan review
Room addition
$75,000 value, addition 400 sq ft
$886.05
$537.00 building permit + $349.05 plan review
New single-family home
$350,000 value, new single-family 2,400 sq ft
$2,515.43
$1,524.50 building permit + $990.93 plan review

How Rochester calculates your permit fee

The city charges a building permit fee using a fee table based on project value, with a $25.00 minimum. Plan review is a separate charge: 65% of the permit fee. Electrical, plumbing and mechanical work gets its own permits.

The fee table

Project valueFee
$1 – $500$25.00
$501 – $2,000$25.00 for the first $500 + $2.00 per additional $100 or fraction
$2,001 – $25,000$55.00 for the first $2,000 + $9.00 per additional $1,000 or fraction
$25,001 – $50,000$262.00 for the first $25,000 + $6.50 per additional $1,000 or fraction
$50,001 – $100,000$424.50 for the first $50,000 + $4.50 per additional $1,000 or fraction
$100,001 – $500,000$649.50 for the first $100,000 + $3.50 per additional $1,000 or fraction
$500,001 – $1,000,000$2,049.50 for the first $500,000 + $3.00 per additional $1,000 or fraction
Over $1,000,000$3,549.50 for the first $1,000,000 + $2.00 per additional $1,000 or fraction

What counts as project value

Not stated in the schedule. Building permit fees are based on 'Total Valuation'; the schedule does not say how valuation is determined.

Worked example: a $350,000 new home

  1. Building permit fee: $649.50 for the first $100,000.00 + $3.50 × 250 per $1,000.00 over = $1,524.50
  2. Plan review fee: 65% of $1,524.50 = $990.93
  3. Total before trade permits: $2,515.43.

Fees people miss

May also apply (not in the totals above)

  • Zoning certificate fee (residential uses): when a zoning certificate is required for the improvement (Planning and Zoning Division); $141.96 on the standard projects.
  • Administrative fee: when the $90 administrative fee listed in the building permit section applies to the permit; $90.00 on the standard projects.
FeeAmount
Working without a permit (1st)When: work started without a permit $100.00 each
Re-inspectionsWhen: re-inspection needed $75.00 per hour, min 1 hour
Additional plan reviewWhen: additional plan review needed $75.00 per hour, min 1 hour
Inspections outside normal business hoursWhen: after-hours inspection requested $75.00 per hour, min 2 hours
Residential footing/foundation permitWhen: separate early footing/foundation permit requested $100.00 each
Zoning certificate double feeWhen: construction or remodeling occurred before the zoning certificate was issued double standard fee

Trade permits are separate. Plumbing: Trade permits: $25 application fee; permit fee $0 for $1-$500, $10 for $501-$1,000, then $10 per each additional $1,000 of valuation; $90 administrative fee listed. Mechanical: Same trade permit schedule; appliance permits fixed (e.g. furnace & A/C $98.50, furnace only $77.50). Electrical: Not listed in the city schedule.

How to apply

  1. Gather your plans and your project's total value.
  2. Submit to Community Development, Building Division through Accela Citizen Access.
  3. Pay the permit and plan review fees when invoiced.

How Rochester compares

A $25,000 remodel costs $432.30 in Rochester: 14% above the national median of $380.00.

A $75,000 addition costs $886.05 in Rochester: 8% above the national median of $820.58.

A $350,000 new home costs $2,515.43 in Rochester: 14% below the national median of $2,918.63.

Same standard projects everywhere, including plan review and required surcharges. All Minnesota places · Compare side by side

Rochester permit fee FAQ

How much is a building permit in Rochester, MN?

A $25,000 remodel: $432.30. A $75,000 addition: $886.05. A $350,000 new single-family: $2,515.43. These include every fee the schedule applies to that project; trade permits are separate.

Is plan review included in the Rochester permit fee?

No. Plan review is charged separately at 65% of the permit fee.

How does Rochester determine project value?

Not stated in the schedule. Building permit fees are based on 'Total Valuation'; the schedule does not say how valuation is determined.

Are electrical, plumbing and mechanical permits included?

No. They are separate permits. Plumbing: Trade permits: $25 application fee; permit fee $0 for $1-$500, $10 for $501-$1,000, then $10 per each additional $1,000 of valuation; $90 administrative fee listed. Mechanical: Same trade permit schedule; appliance permits fixed (e.g. furnace & A/C $98.50, furnace only $77.50). Electrical: Not listed in the city schedule.

When did these Rochester fees take effect?

The schedule does not state an effective date. We last checked it against the official source on Nov 5, 2026.