Building Permit Fees in Lakeville, MN (2026)

Lakeville prices building permits with a fee table based on project value, with a $30.00 minimum, then charges plan review at 65% of the permit fee. Enter your project to see the exact math.

  • Official city schedule
  • Effective Jan 1, 2026
  • Verified Nov 5, 2026
Minimum fee
$30.00
Plan review
65%
$75k addition
$1,434

Permit fee calculator

Lakeville schedule, eff. Jan 1, 2026
Project type
Estimated permit fees $1,434.26
  1. 1. Building permit fee
    $681.75 for the first $50,000.00 + $7.50 × 25 per $1,000.00 over
    $869.25
  2. 2. Plan review fee
    65% of $869.25
    $565.01

Fees are estimates based on the official schedule linked below. Confirm with the permit office before applying. Separate electrical, plumbing, mechanical, fire, impact, utility and school fees are usually not included unless they are listed. BuildingPermitCost is not a government permit office, and this is not legal advice.

What common projects cost

Kitchen or bath remodel
$25,000 value, remodel 300 sq ft
$681.45
$413.00 building permit + $268.45 plan review
Room addition
$75,000 value, addition 400 sq ft
$1,434.26
$869.25 building permit + $565.01 plan review
New single-family home
$350,000 value, new single-family 2,400 sq ft
$4,218.64
$2,556.75 building permit + $1,661.89 plan review

How Lakeville calculates your permit fee

The city charges a building permit fee using a fee table based on project value, with a $30.00 minimum. Plan review is a separate charge: 65% of the permit fee. Electrical, plumbing and mechanical work gets its own permits.

The fee table

Project valueFee
$1 – $500$30.00
$501 – $2,000$30.00 for the first $500 + $3.25 per additional $100 or fraction
$2,001 – $25,000$73.75 for the first $2,000 + $14.75 per additional $1,000 or fraction
$25,001 – $50,000$413.00 for the first $25,000 + $10.75 per additional $1,000 or fraction
$50,001 – $100,000$681.75 for the first $50,000 + $7.50 per additional $1,000 or fraction
$100,001 – $500,000$1,056.75 for the first $100,000 + $6.00 per additional $1,000 or fraction
$500,001 – $1,000,000$3,456.75 for the first $500,000 + $5.00 per additional $1,000 or fraction
Over $1,000,000$5,956.75 for the first $1,000,000 + $4.00 per additional $1,000 or fraction

What counts as project value

Not stated in the schedule. The building permit table is by 'Total Valuation'; the fee schedule does not say how valuation is determined.

Worked example: a $350,000 new home

  1. Building permit fee: $1,056.75 for the first $100,000.00 + $6.00 × 250 per $1,000.00 over = $2,556.75
  2. Plan review fee: 65% of $2,556.75 = $1,661.89
  3. Total before trade permits: $4,218.64.

Fees people miss

May also apply (not in the totals above)

  • Watermain unit charge (low/medium-density residential): when new low- or medium-density dwelling unit (per unit, paid with building permit); $4,100.00 on the standard projects.
  • Sanitary sewer connection charge: when new dwelling unit (per unit, paid with building permit); $825.00 on the standard projects.
  • MCES SAC unit charge: when new dwelling unit (per SAC unit, paid with building permit; set by Metropolitan Council Environmental Services); $2,485.00 on the standard projects.
FeeAmount
Landscaping escrowWhen: new construction requiring landscaping escrow $1,000.00 escrow
Erosion control/grading certification escrowWhen: new construction requiring erosion control escrow $1,000.00 escrow
Storm sewer charge, single-family residentialWhen: development subject to storm sewer charge $0.18 per sq ft
Park dedication fee, low-density residentialWhen: development/platting subject to park dedication $6,007.00 per dwelling unit
Sanitary sewer availability chargeWhen: new unit subject to availability charge $327.00 per unit

Trade permits are separate. Plumbing: Residential minimum (repairs/alterations) $70; complete installation $150; commercial 1.5% of contract/valuation (min $70). Mechanical: Heating: residential minimum $70; complete installation $150; commercial 1.5% (min $70). Electrical: Residential: repairs $55 (one trip), additions/remodels $110 (two trips), new installation $220 (up to three trips); commercial 1.5% to $10,000 and 1.0% above (min $55).

How to apply

  1. Gather your plans and your project's total value.
  2. Submit to Building Inspections.
  3. Pay the permit and plan review fees when invoiced.

How Lakeville compares

A $25,000 remodel costs $681.45 in Lakeville: 79% above the national median of $380.00.

A $75,000 addition costs $1,434.26 in Lakeville: 75% above the national median of $820.58.

A $350,000 new home costs $4,218.64 in Lakeville: 45% above the national median of $2,918.63.

Same standard projects everywhere, including plan review and required surcharges. All Minnesota places · Compare side by side

Lakeville permit fee FAQ

How much is a building permit in Lakeville, MN?

A $25,000 remodel: $681.45. A $75,000 addition: $1,434.26. A $350,000 new single-family: $4,218.64. These include every fee the schedule applies to that project; trade permits are separate.

Is plan review included in the Lakeville permit fee?

No. Plan review is charged separately at 65% of the permit fee.

How does Lakeville determine project value?

Not stated in the schedule. The building permit table is by 'Total Valuation'; the fee schedule does not say how valuation is determined.

Are electrical, plumbing and mechanical permits included?

No. They are separate permits. Plumbing: Residential minimum (repairs/alterations) $70; complete installation $150; commercial 1.5% of contract/valuation (min $70). Mechanical: Heating: residential minimum $70; complete installation $150; commercial 1.5% (min $70). Electrical: Residential: repairs $55 (one trip), additions/remodels $110 (two trips), new installation $220 (up to three trips); commercial 1.5% to $10,000 and 1.0% above (min $55).

When did these Lakeville fees take effect?

The schedule is effective Jan 1, 2026 (“2026 Fee Schedule, Effective January 1, 2026”). We last checked it against the official source on Nov 5, 2026.