Building Permit Fees in Moreno Valley, CA (2026)

Moreno Valley prices building permits with a fee table based on floor area, plus a $30.00 application fee, then charges plan review at its own fee table. Enter your project to see the exact math.

  • Official city schedule
  • Effective not stated
  • Verified Nov 4, 2026
Minimum fee
—
Plan review
Separate
$75k addition
$1,483

Permit fee calculator

Moreno Valley schedule
Project type
Estimated permit fees $1,482.50
  1. 1. Building permit fee
    table value for 400 sq ft: $770.00
    $770.00
  2. 2. Application fee
    fixed
    $30.00
  3. 3. Plan review fee
    table value for 400 sq ft: $615.00
    $615.00
  4. 4. Training surcharge (AB 717)
    fixed
    $3.00
  5. 5. Technology maintenance fee
    fixed
    $3.00
  6. 6. Document archive fee
    10% of $615.00
    $61.50

Fees are estimates based on the official schedule linked below. Confirm with the permit office before applying. Separate electrical, plumbing, mechanical, fire, impact, utility and school fees are usually not included unless they are listed. BuildingPermitCost is not a government permit office, and this is not legal advice.

What common projects cost

Kitchen or bath remodel
$25,000 value, remodel 300 sq ft
$1,482.50
$770.00 building permit + $30.00 application + $615.00 plan review + $3.00 training surcharge (ab 717) + $3.00 technology maintenance + $61.50 document archive
Room addition
$75,000 value, addition 400 sq ft
$1,482.50
$770.00 building permit + $30.00 application + $615.00 plan review + $3.00 training surcharge (ab 717) + $3.00 technology maintenance + $61.50 document archive
New single-family home
$350,000 value, new single-family 2,400 sq ft
$3,869.50
$2,310.00 building permit + $30.00 application + $1,385.00 plan review + $3.00 training surcharge (ab 717) + $3.00 technology maintenance + $138.50 document archive

How Moreno Valley calculates your permit fee

The city charges a building permit fee using a fee table based on floor area, plus a $30.00 application fee. Plan review is a separate charge: its own fee table. Electrical, plumbing and mechanical work gets its own permits.

The fee table

One and two family dwelling, new (R-3), construction type IIB, IIIA, IV

Floor areaFee
0 sq ft – 2,499 sq ft$2,885.00
2,499 sq ft – 3,999 sq ft$3,465.00
3,999 sq ft – 5,999 sq ft$3,850.00
5,999 sq ft – 7,999 sq ft$4,810.00
7,999 sq ft – 8,000 sq ft$5,390.00
Over 8,000 sq ft$5,390.00 for the first 8,000 sq ft + $0.67 per additional sq ft or fraction

Plus an application fee of $30.00.

One and two family dwelling, new (R-3), construction type IA, IB, IIA

Floor areaFee
0 sq ft – 2,499 sq ft$4,330.00
2,499 sq ft – 3,999 sq ft$5,195.00
3,999 sq ft – 5,999 sq ft$5,775.00
5,999 sq ft – 7,999 sq ft$7,215.00
7,999 sq ft – 8,000 sq ft$8,080.00
Over 8,000 sq ft$8,080.00 for the first 8,000 sq ft + $1.01 per additional sq ft or fraction

Plus an application fee of $30.00.

One and two family dwelling, new (R-3), construction type IIIB, VA, VB

Floor areaFee
0 sq ft – 2,499 sq ft$2,310.00
2,499 sq ft – 3,999 sq ft$2,770.00
3,999 sq ft – 5,999 sq ft$3,080.00
5,999 sq ft – 7,999 sq ft$3,850.00
7,999 sq ft – 8,000 sq ft$4,310.00
Over 8,000 sq ft$4,310.00 for the first 8,000 sq ft + $0.54 per additional sq ft or fraction

Plus an application fee of $30.00.

R-3 residential remodel or addition, construction type IIIB, VA, VB

Floor areaFee
0 sq ft – 599 sq ft$770.00
599 sq ft – 999 sq ft$1,230.00
999 sq ft – 1,499 sq ft$1,540.00
1,499 sq ft – 1,999 sq ft$1,845.00
1,999 sq ft – 2,000 sq ft$2,310.00
Over 2,000 sq ft$2,310.00 for the first 2,000 sq ft + $1.15 per additional sq ft or fraction

Plus an application fee of $30.00.

R-3 residential remodel or addition, construction type IIB, IIIA, IV

Floor areaFee
0 sq ft – 599 sq ft$960.00
599 sq ft – 999 sq ft$1,540.00
999 sq ft – 1,499 sq ft$1,925.00
1,499 sq ft – 1,999 sq ft$2,310.00
1,999 sq ft – 2,000 sq ft$2,885.00
Over 2,000 sq ft$2,885.00 for the first 2,000 sq ft + $1.44 per additional sq ft or fraction

Plus an application fee of $30.00.

R-3 residential remodel or addition, construction type IA, IB, IIA

Floor areaFee
0 sq ft – 599 sq ft$1,445.00
599 sq ft – 999 sq ft$2,310.00
999 sq ft – 1,499 sq ft$2,885.00
1,499 sq ft – 1,999 sq ft$3,465.00
1,999 sq ft – 2,000 sq ft$4,330.00
Over 2,000 sq ft$4,330.00 for the first 2,000 sq ft + $2.16 per additional sq ft or fraction

Plus an application fee of $30.00.

Surcharges

  • Training surcharge (AB 717): $3.00
  • Technology maintenance fee: $3.00
  • Document archive fee: 10% of the plan review fee

What counts as project value

Floor area (square feet). Building plan check and inspection fees are set by occupancy, construction type and square footage ('per project base @ X s.f.'), with a per-sq-ft modifier only above the top size (8,000 sf new dwellings; 2,000 sf remodels/additions). Valuation is not used.

Worked example: a $350,000 new home

  1. Building permit fee: table value for 2,400 sq ft: $2,310.00 = $2,310.00
  2. Application fee: fixed = $30.00
  3. Plan review fee: table value for 2,400 sq ft: $1,385.00 = $1,385.00
  4. Training surcharge (AB 717): fixed = $3.00
  5. Technology maintenance fee: fixed = $3.00
  6. Document archive fee: 10% of $1,385.00 = $138.50
  7. Total before trade permits: $3,869.50.

Fees people miss

FeeAmount
Residential repeat/subsequent lot plan checkWhen: repeat tract lots $305.00 per project
Certificate of occupancy inspection, residentialWhen: when a CO inspection is required $115.00 each
Temporary certificate of occupancyWhen: temporary CO requested $628.00 each
Supplemental inspection / supplemental plan reviewWhen: extra service $154.00 per hour
Deferred submittal plan checkWhen: deferred submittals $310.00 per hour, 2-hour minimum
Expedited plan checkWhen: optional expedited review actual cost (outsourced contract rate)
Investigative fee (work without permit)When: work started without a permit equal to the permit fees
MEP permit processing/filing feeWhen: separate mechanical/plumbing/electrical permit $51.00 per project

Trade permits are separate. Mechanical: Processing/filing fee $51 per project; simple project inspection $230 (up to 3 'simple' items, $51 each additional); 'complex' items priced individually (e.g. furnace up to 100,000 Btu/hr $230). Plumbing: Same simple/complex structure; e.g. septic building sewer plan check $45 + inspection $381. Electrical: Same simple/complex structure (pages 17–20); not fully extracted.

How to apply

  1. Gather your plans and your project's total value and floor area.
  2. Submit to Community Development, Building and Safety Division through SimpliCITY.
  3. Pay the permit and plan review fees when invoiced.
  4. Questions: (951) 413-3350

How Moreno Valley compares

A $25,000 remodel costs $1,482.50 in Moreno Valley: about 3.9 times the national median of $380.00, and the 15th highest of 43 places we cover in California (state median $1,263.01).

A $75,000 addition costs $1,482.50 in Moreno Valley: 81% above the national median of $820.58, and the 5th lowest of 45 places we cover in California (state median $2,473.00).

A $350,000 new home costs $3,869.50 in Moreno Valley: 33% above the national median of $2,918.63, and the 2nd lowest of 47 places we cover in California (state median $6,927.50).

Same standard projects everywhere, including plan review and required surcharges. All California places · Compare side by side

Moreno Valley permit fee FAQ

How much is a building permit in Moreno Valley, CA?

A $25,000 remodel: $1,482.50. A $75,000 addition: $1,482.50. A $350,000 new single-family: $3,869.50. These include every fee the schedule applies to that project; trade permits are separate.

Is plan review included in the Moreno Valley permit fee?

No. Plan review is charged separately at its own fee table.

How does Moreno Valley determine project value?

Floor area (square feet). Building plan check and inspection fees are set by occupancy, construction type and square footage ('per project base @ X s.f.'), with a per-sq-ft modifier only above the top size (8,000 sf new dwellings; 2,000 sf remodels/additions). Valuation is not used.

Are electrical, plumbing and mechanical permits included?

No. They are separate permits. Mechanical: Processing/filing fee $51 per project; simple project inspection $230 (up to 3 'simple' items, $51 each additional); 'complex' items priced individually (e.g. furnace up to 100,000 Btu/hr $230). Plumbing: Same simple/complex structure; e.g. septic building sewer plan check $45 + inspection $381. Electrical: Same simple/complex structure (pages 17–20); not fully extracted.

When did these Moreno Valley fees take effect?

The schedule does not state an effective date. We last checked it against the official source on Nov 4, 2026.