How Moreno Valley calculates your permit fee
The city charges a building permit fee using a fee table based on floor area, plus a $30.00 application fee. Plan review is a separate charge: its own fee table. Electrical, plumbing and mechanical work gets its own permits.
The fee table
One and two family dwelling, new (R-3), construction type IIB, IIIA, IV
| Floor area | Fee |
|---|---|
| 0 sq ft – 2,499 sq ft | $2,885.00 |
| 2,499 sq ft – 3,999 sq ft | $3,465.00 |
| 3,999 sq ft – 5,999 sq ft | $3,850.00 |
| 5,999 sq ft – 7,999 sq ft | $4,810.00 |
| 7,999 sq ft – 8,000 sq ft | $5,390.00 |
| Over 8,000 sq ft | $5,390.00 for the first 8,000 sq ft + $0.67 per additional sq ft or fraction |
Plus an application fee of $30.00.
One and two family dwelling, new (R-3), construction type IA, IB, IIA
| Floor area | Fee |
|---|---|
| 0 sq ft – 2,499 sq ft | $4,330.00 |
| 2,499 sq ft – 3,999 sq ft | $5,195.00 |
| 3,999 sq ft – 5,999 sq ft | $5,775.00 |
| 5,999 sq ft – 7,999 sq ft | $7,215.00 |
| 7,999 sq ft – 8,000 sq ft | $8,080.00 |
| Over 8,000 sq ft | $8,080.00 for the first 8,000 sq ft + $1.01 per additional sq ft or fraction |
Plus an application fee of $30.00.
One and two family dwelling, new (R-3), construction type IIIB, VA, VB
| Floor area | Fee |
|---|---|
| 0 sq ft – 2,499 sq ft | $2,310.00 |
| 2,499 sq ft – 3,999 sq ft | $2,770.00 |
| 3,999 sq ft – 5,999 sq ft | $3,080.00 |
| 5,999 sq ft – 7,999 sq ft | $3,850.00 |
| 7,999 sq ft – 8,000 sq ft | $4,310.00 |
| Over 8,000 sq ft | $4,310.00 for the first 8,000 sq ft + $0.54 per additional sq ft or fraction |
Plus an application fee of $30.00.
R-3 residential remodel or addition, construction type IIIB, VA, VB
| Floor area | Fee |
|---|---|
| 0 sq ft – 599 sq ft | $770.00 |
| 599 sq ft – 999 sq ft | $1,230.00 |
| 999 sq ft – 1,499 sq ft | $1,540.00 |
| 1,499 sq ft – 1,999 sq ft | $1,845.00 |
| 1,999 sq ft – 2,000 sq ft | $2,310.00 |
| Over 2,000 sq ft | $2,310.00 for the first 2,000 sq ft + $1.15 per additional sq ft or fraction |
Plus an application fee of $30.00.
R-3 residential remodel or addition, construction type IIB, IIIA, IV
| Floor area | Fee |
|---|---|
| 0 sq ft – 599 sq ft | $960.00 |
| 599 sq ft – 999 sq ft | $1,540.00 |
| 999 sq ft – 1,499 sq ft | $1,925.00 |
| 1,499 sq ft – 1,999 sq ft | $2,310.00 |
| 1,999 sq ft – 2,000 sq ft | $2,885.00 |
| Over 2,000 sq ft | $2,885.00 for the first 2,000 sq ft + $1.44 per additional sq ft or fraction |
Plus an application fee of $30.00.
R-3 residential remodel or addition, construction type IA, IB, IIA
| Floor area | Fee |
|---|---|
| 0 sq ft – 599 sq ft | $1,445.00 |
| 599 sq ft – 999 sq ft | $2,310.00 |
| 999 sq ft – 1,499 sq ft | $2,885.00 |
| 1,499 sq ft – 1,999 sq ft | $3,465.00 |
| 1,999 sq ft – 2,000 sq ft | $4,330.00 |
| Over 2,000 sq ft | $4,330.00 for the first 2,000 sq ft + $2.16 per additional sq ft or fraction |
Plus an application fee of $30.00.
Surcharges
- Training surcharge (AB 717): $3.00
- Technology maintenance fee: $3.00
- Document archive fee: 10% of the plan review fee
What counts as project value
Floor area (square feet). Building plan check and inspection fees are set by occupancy, construction type and square footage ('per project base @ X s.f.'), with a per-sq-ft modifier only above the top size (8,000 sf new dwellings; 2,000 sf remodels/additions). Valuation is not used.
Worked example: a $350,000 new home
- Building permit fee: table value for 2,400 sq ft: $2,310.00 = $2,310.00
- Application fee: fixed = $30.00
- Plan review fee: table value for 2,400 sq ft: $1,385.00 = $1,385.00
- Training surcharge (AB 717): fixed = $3.00
- Technology maintenance fee: fixed = $3.00
- Document archive fee: 10% of $1,385.00 = $138.50
- Total before trade permits: $3,869.50.
Fees people miss
| Fee | Amount |
|---|---|
| Residential repeat/subsequent lot plan checkWhen: repeat tract lots | $305.00 per project |
| Certificate of occupancy inspection, residentialWhen: when a CO inspection is required | $115.00 each |
| Temporary certificate of occupancyWhen: temporary CO requested | $628.00 each |
| Supplemental inspection / supplemental plan reviewWhen: extra service | $154.00 per hour |
| Deferred submittal plan checkWhen: deferred submittals | $310.00 per hour, 2-hour minimum |
| Expedited plan checkWhen: optional expedited review | actual cost (outsourced contract rate) |
| Investigative fee (work without permit)When: work started without a permit | equal to the permit fees |
| MEP permit processing/filing feeWhen: separate mechanical/plumbing/electrical permit | $51.00 per project |
Trade permits are separate. Mechanical: Processing/filing fee $51 per project; simple project inspection $230 (up to 3 'simple' items, $51 each additional); 'complex' items priced individually (e.g. furnace up to 100,000 Btu/hr $230). Plumbing: Same simple/complex structure; e.g. septic building sewer plan check $45 + inspection $381. Electrical: Same simple/complex structure (pages 17–20); not fully extracted.
How to apply
- Gather your plans and your project's total value and floor area.
- Submit to Community Development, Building and Safety Division through SimpliCITY.
- Pay the permit and plan review fees when invoiced.
- Questions: (951) 413-3350