How Madison calculates your permit fee
The city charges a building permit fee using $0.10 per square foot, with a $25.00 minimum. Plan review is a separate charge: a flat $100.00. Electrical, plumbing and mechanical work gets its own permits.
The fee table
Group 1: single/two-family (and R-2, R-3, R-4) new buildings and additions
$0.10 per square foot, with a $25.00 minimum.
Alterations and repairs to existing structures
$11.00 per $1,000 of project value, with a $25.00 minimum.
Group 2 commercial (A, B, E, H, I, M, R-1) new construction and additions
$0.18 per square foot, with a $25.00 minimum.
Added to every matching permit
- Electrical inspection (Group 1): $0.09 per square foot, with a $25.00 minimum (Residential · new construction, additions)
- Plumbing inspection (Group 1): $0.09 per square foot, with a $25.00 minimum (Residential · new construction, additions)
- HVAC inspection (Group 1): $0.09 per square foot, with a $25.00 minimum (Residential · new construction, additions)
- Electrical inspection (Group 2 commercial): $0.11 per square foot, with a $25.00 minimum (Commercial · new construction, additions)
- Plumbing inspection (Group 2 commercial): $0.11 per square foot, with a $25.00 minimum (Commercial · new construction, additions)
- HVAC inspection (Group 2 commercial): $0.11 per square foot, with a $25.00 minimum (Commercial · new construction, additions)
Surcharges
- Zoning review fee (MGO 28.206): $0.03 per sq ft, minimum $25.00
What counts as project value
Floor area (square feet). New buildings and additions are charged per square foot of total building area 'including all floor levels, attached garages, porches, balconies and decks'. Alterations and repairs to existing structures are charged per $1,000 of value; the page does not say how value is determined.
Worked example: a $350,000 new home
- Building permit fee: 2,400 sq ft × $0.10 = $240.00
- Plan review fee: flat = $100.00
- Electrical inspection (Group 1): 2,400 sq ft × $0.09 = $216.00
- Plumbing inspection (Group 1): 2,400 sq ft × $0.09 = $216.00
- HVAC inspection (Group 1): 2,400 sq ft × $0.09 = $216.00
- Zoning review fee (MGO 28.206): 2,400 sq ft × $0.03 = $72.00
- Total before trade permits: $1,060.00.
Fees people miss
| Fee | Amount |
|---|---|
| Erosion control fee | $0.01 per sq ft of lot area |
| State Seal fee (DSPS) | as charged by DSPS |
| Revisions to previously examined plansWhen: plan revisions | $100.00 each |
| Early start permit (commercial only)When: optional early start | $50.00 each |
| Certificate of occupancy | $10.00 first certificate |
Trade permits are separate. Electrical: New buildings/additions: per sq ft by group (Group 1 $0.09). Existing buildings: new or altered openings $25 for the first ten plus $1 each additional; service replacement $50 per panel. Plumbing: New buildings/additions: per sq ft by group (Group 1 $0.09). Existing buildings: $8 per new or altered fixture, minimum $25. Plumbing plan review per SPS 302.64. Mechanical: New buildings/additions: per sq ft by group (Group 1 $0.09). Replacement heating equipment $25 up to 100,000 BTU, $50 to 165,000, $75 above; A/C unit $25; ductless split $25.
How to apply
- Gather your plans and your project's total value and floor area.
- Submit to Building Inspection Division, Department of Planning and Community and Economic Development (Development Services Center).
- Pay the permit and plan review fees when invoiced.