Spokane prices building permits with a fee table based on project value, plus a $65.00 application fee, with a $73.00 minimum, then charges plan review at 50% of the permit fee. Enter your project to see the exact math.

  • Official city schedule
  • Effective Jan 1, 2026
  • Verified Nov 4, 2026
Minimum fee
$73.00
Plan review
50%
$75k addition
$1,088

Permit fee calculator

Spokane schedule, eff. Jan 1, 2026
Project type
Estimated permit fees $1,087.78
  1. 1. Building permit fee
    $622.00 for the first $50,000.00 + $7.00 × 25 per $1,000.00 over
    $797.00
  2. 2. Application fee
    fixed
    $65.00
  3. 3. Plan review fee
    25% of $797.00
    $199.25
  4. 4. Technology Fee
    2.5% of $1,061.25
    $26.53

May also apply (not in the total)

  • Early Start and Fast Track Approval
    When: optional early start / fast track
    $199.25

Fees are estimates based on the official schedule linked below. Confirm with the permit office before applying. Separate electrical, plumbing, mechanical, fire, impact, utility and school fees are usually not included unless they are listed. BuildingPermitCost is not a government permit office, and this is not legal advice.

What common projects cost

Kitchen or bath remodel
$25,000 value, remodel 300 sq ft
$447.93
$372.00 building permit + $65.00 application + $10.93 technology
Room addition
$75,000 value, addition 400 sq ft
$1,087.78
$797.00 building permit + $65.00 application + $199.25 plan review + $26.53 technology
New single-family home
$350,000 value, new single-family 2,400 sq ft
$3,482.95
$2,222.00 building permit + $65.00 application + $1,111.00 plan review + $84.95 technology

How Spokane calculates your permit fee

The city charges a building permit fee using a fee table based on project value, plus a $65.00 application fee, with a $73.00 minimum. Plan review is a separate charge: 50% of the permit fee.

The fee table

Project valueFee
$1 – $2,000$73.00
$2,001 – $25,000$73.00 for the first $2,000 + $13.00 per additional $1,000 or fraction
$25,001 – $50,000$372.00 for the first $25,000 + $10.00 per additional $1,000 or fraction
$50,001 – $100,000$622.00 for the first $50,000 + $7.00 per additional $1,000 or fraction
$100,001 – $500,000$972.00 for the first $100,000 + $5.00 per additional $1,000 or fraction
$500,001 – $1,000,000$2,972.00 for the first $500,000 + $4.00 per additional $1,000 or fraction
Over $1,000,000$4,972.00 for the first $1,000,000 + $3.00 per additional $1,000 or fraction

Plus an application fee of $65.00.

Surcharges

  • Technology Fee: 2.5% of the fee total

What counts as project value

ICC Building Valuation Data table. Fees are by job value. The schedule says building permit fees are not automatically adjusted 'because updates occur semi-annually through the International Code Council (ICC) published updates', implying job value is set from ICC Building Valuation Data; the exact rule (e.g. greater of contract value or ICC valuation) is not stated in this schedule.

Worked example: a $350,000 new home

  1. Building permit fee: $972.00 for the first $100,000.00 + $5.00 × 250 per $1,000.00 over = $2,222.00
  2. Application fee: fixed = $65.00
  3. Plan review fee: 50% of $2,222.00 = $1,111.00
  4. Technology Fee: 2.5% of $3,398.00 = $84.95
  5. Total before trade permits: $3,482.95.

Fees people miss

May also apply (not in the totals above)

  • Early Start and Fast Track Approval: when optional early start / fast track; $93.00 on the standard projects.
FeeAmount
State Building Code Fee State Determined Fee
Development Services Review FeeWhen: when development services review applies (not stated) $119.00 each
Re-inspection feeWhen: re-inspection $156.00 each
Work done without permit / investigative feeWhen: work without permit $311.00 greater of 2x inspection fee(s) or $311
Inspection outside normal working hoursWhen: after hours $119.00 per hour (2-hr minimum)
Additional, excessive or phased reviewsWhen: additional reviews 50% of original review fee
Revision reviewWhen: revision $119.00 per hour
Permit or application extensionWhen: extension $46.60 each
Plan review, SFR & duplex accessory structure remodelsWhen: accessory structure remodel 25% of job value fee

How to apply

  1. Gather your plans and your project's total value.
  2. Submit to Development Services Center online through the permit portal.
  3. Pay the permit and plan review fees when invoiced.
  4. Questions: City Hall, 808 W Spokane Falls Blvd, Spokane, WA

How Spokane compares

A $25,000 remodel costs $447.93 in Spokane: 18% above the national median of $380.00, and the lowest of 10 places we cover in Washington (state median $652.06).

A $75,000 addition costs $1,087.78 in Spokane: 33% above the national median of $820.58, and the 2nd lowest of 10 places we cover in Washington (state median $1,357.44).

A $350,000 new home costs $3,482.95 in Spokane: 19% above the national median of $2,918.63, and the 3rd lowest of 10 places we cover in Washington (state median $3,956.19).

Same standard projects everywhere, including plan review and required surcharges. All Washington places · Compare side by side

Spokane permit fee FAQ

How much is a building permit in Spokane, WA?

A $25,000 remodel: $447.93. A $75,000 addition: $1,087.78. A $350,000 new single-family: $3,482.95. These include every fee the schedule applies to that project; trade permits are separate.

Is plan review included in the Spokane permit fee?

No. Plan review is charged separately at 50% of the permit fee.

How does Spokane determine project value?

ICC Building Valuation Data table. Fees are by job value. The schedule says building permit fees are not automatically adjusted 'because updates occur semi-annually through the International Code Council (ICC) published updates', implying job value is set from ICC Building Valuation Data; the exact rule (e.g. greater of contract value or ICC valuation) is not stated in this schedule.

When did these Spokane fees take effect?

The schedule is effective Jan 1, 2026 (“Development Fee Schedule 2026 (annual adjustment effective January 1, 2026; building permit fees excluded from the automatic adjustment)”). We last checked it against the official source on Nov 4, 2026.