How Savannah calculates your permit fee
The city charges a building permit fee using a fee table based on project value, with a $40.00 minimum. Plan review is a separate charge: its own fee table.
The fee table
Residential new construction and additions (all-inclusive building permit)
| Project value | Fee |
|---|---|
| $1 – $5,000,000 | $8.00 per $1,000 |
| $5,000,001 – $10,000,000 | $40,000.00 for the first $5,000,000 + $4.00 per additional $1,000 |
| Over $10,000,000 | $60,000.00 for the first $10,000,000 + $2.00 per additional $1,000 |
Residential general interior renovations under $75,000
A flat $150.00.
Residential renovations costing $75,000+
| Project value | Fee |
|---|---|
| $1 – $5,000,000 | $8.00 per $1,000 |
| $5,000,001 – $10,000,000 | $40,000.00 for the first $5,000,000 + $4.00 per additional $1,000 |
| Over $10,000,000 | $60,000.00 for the first $10,000,000 + $2.00 per additional $1,000 |
Commercial new construction, additions and renovations costing $75,000+
| Project value | Fee |
|---|---|
| $1 – $5,000,000 | $8.00 per $1,000 |
| $5,000,001 – $10,000,000 | $40,000.00 for the first $5,000,000 + $4.00 per additional $1,000 |
| Over $10,000,000 | $60,000.00 for the first $10,000,000 + $2.00 per additional $1,000 |
Commercial general interior renovations under $75,000
A flat $350.00.
Surcharges
- Technology Fee: $5.00
What counts as project value
Higher of your bid or the valuation table. Construction value is the greater of all labor, materials, profit and overhead; contract cost; or covered square feet x $80.00 (residential new construction) / $125.00 (commercial new construction).
Worked example: a $350,000 new home
- Building permit fee: $0.00 for the first $0.00 + $8.00 × 350 per $1,000.00 over = $2,800.00
- Plan review fee: table value for $350,000.00: $200.00 = $200.00
- Technology Fee: fixed = $5.00
- Total before trade permits: $3,005.00.
Fees people miss
May also apply (not in the totals above)
- Phased permit fee: when phased permit; $75.00 on the standard projects.
| Fee | Amount |
|---|---|
| Master Home Plan plan reviewWhen: master home plan | $200.00 each |
| Revisions to approved building plansWhen: plan revisions | original plan review fee, $200 max |
| 90 day permit extensionWhen: extension requested | $500.00 minimum |
| Permit reinstatementWhen: reinstatement | $500.00 minimum |
| Code modification interpretation requestWhen: requested | $300.00 each |
| Temporary Certificate of Occupancy reviewWhen: TCO requested | $500.00 greater of $500 or 5% of permit fee |
| Re-inspection feeWhen: reinspection | $100.00 each |
| After-hours inspectionWhen: after hours | $50.00 per hour |
| Working without a permit penaltyWhen: work without permit | $500.00 greater of $500 or double permit fee |
| Site plan reviewWhen: site development | $1,200.00 each |
How to apply
- Gather your plans and your project's total value.
- Submit to Development Services.
- Pay the permit and plan review fees when invoiced.
- Questions: 912.651.6530 · 20 Interchange Dr., P.O. Box 1027, Savannah, GA 31402