How San Francisco calculates your permit fee
The city charges a building permit fee using a fee table based on project value. Plan review is a separate charge: its own fee table.
The fee table
| Project value | Fee |
|---|---|
| $1 – $500 | $206.00 |
| $501 – $2,000 | $206.00 for the first $500 + $4.00 per additional $100 or fraction |
| $2,001 – $50,000 | $266.00 for the first $2,000 + $8.56 per additional $1,000 or fraction |
| $50,001 – $200,000 | $677.00 for the first $50,000 + $4.83 per additional $1,000 or fraction |
| $200,001 – $500,000 | $1,402.00 for the first $200,000 + $4.21 per additional $1,000 or fraction |
| $500,001 – $1,000,000 | $2,666.00 for the first $500,000 + $3.63 per additional $1,000 or fraction |
| $1,000,001 – $5,000,000 | $4,481.00 for the first $1,000,000 + $2.93 per additional $1,000 or fraction |
| $5,000,001 – $50,000,000 | $16,211.00 for the first $5,000,000 + $1.55 per additional $1,000 or fraction |
| $50,000,001 – $100,000,000 | $86,181.00 for the first $50,000,000 + $1.74 per additional $1,000 or fraction |
| $100,000,001 – $200,000,000 | $173,272.00 for the first $100,000,000 + $2.82 per additional $1,000 or fraction |
| Over $200,000,000 | $455,407.00 for the first $200,000,000 + $2.82 per additional $1,000 or fraction |
Surcharges
- State-mandated fee (Building Standards Commission, BSASRF): $0.04 per $1,000 of value, minimum $1.00
- Strong Motion Instrumentation Program (SMIP) fee, Group R: $0.13 per $1,000 of value, minimum $0.50
- Strong Motion Instrumentation Program (SMIP) fee, non-R occupancies: $0.28 per $1,000 of value, minimum $0.50
What counts as project value
Local valuation table. Valuation is calculated with the DBI Cost Schedule (2022 edition, published January 1, 2023; unit prices per gross floor area) and represents the value at completion of all work, including finish, roofing, MEP and permanently installed equipment (SFBC 107A.2).
Worked example: a $350,000 new home
- Building permit fee: $1,402.00 for the first $200,000.00 + $4.21 × 150 per $1,000.00 over = $2,033.50
- Plan review fee: $4,011.00 for the first $200,000.00 + $13.31 × 150 per $1,000.00 over = $6,007.50
- State-mandated fee (Building Standards Commission, BSASRF): $350,000.00 ÷ 1,000 × $0.04 = $14.00
- Strong Motion Instrumentation Program (SMIP) fee, Group R: $350,000.00 ÷ 1,000 × $0.13 = $45.50
- Total before trade permits: $8,100.50.
Fees people miss
May also apply (not in the totals above)
- Lead safe work practices surcharge: when alteration permits for R3 (one/two-family) and E3 buildings constructed before 1979; $5.00 on the standard projects.
| Fee | Amount |
|---|---|
| Plan review not covered in Table 1A-AWhen: plan review not covered by Table 1A-A | $602.00 per hour |
| Back check feeWhen: revisions / back check | $602.00 per hour |
| Pre-application plan reviewWhen: pre-application review requested | $602.00 per hour |
| Site permit feeWhen: site permit process | 25% of Table 1A-A plan review fee |
| Premium plan reviewWhen: premium (expedited) review requested | 50% of plan review fee plus $1,000 |
| Reduced plan reviewWhen: when reduced plan review applies | 50% of plan review fee |
| Third-party experts and other permit related actionsWhen: third-party review | actual cost, time and materials |
How to apply
- Gather your plans and your project's total value.
- Submit to Department of Building Inspection.
- Pay the permit and plan review fees when invoiced.
- Questions: 628-652-3200 · 49 South Van Ness Avenue, San Francisco, CA 94103