Building Permit Fees in Honolulu, HI (2026)

Honolulu prices building permits with a fee table based on project value, with a $20.00 minimum, then charges plan review at 20% of the permit fee. Enter your project to see the exact math.

  • Official city schedule
  • Effective not stated
  • Verified Nov 4, 2026
Minimum fee
$20.00
Plan review
20%
$75k addition
$1,603

Permit fee calculator

Honolulu schedule
Project type
Estimated permit fees $1,603.20
  1. 1. Building permit fee
    $986.00 for the first $50,000.00 + $14.00 × 25 per $1,000.00 over
    $1,336.00
  2. 2. Plan review fee
    20% of $1,336.00
    $267.20

Fees are estimates based on the official schedule linked below. Confirm with the permit office before applying. Separate electrical, plumbing, mechanical, fire, impact, utility and school fees are usually not included unless they are listed. BuildingPermitCost is not a government permit office, and this is not legal advice.

What common projects cost

Kitchen or bath remodel
$25,000 value, remodel 300 sq ft
$638.40
$532.00 building permit + $106.40 plan review
Room addition
$75,000 value, addition 400 sq ft
$1,603.20
$1,336.00 building permit + $267.20 plan review
New single-family home
$350,000 value, new single-family 2,400 sq ft
$5,040.00
$4,200.00 building permit + $840.00 plan review

How Honolulu calculates your permit fee

The city charges a building permit fee using a fee table based on project value, with a $20.00 minimum. Plan review is a separate charge: 20% of the permit fee.

The fee table

Project valueFee
$1 – $500$20.00
$501 – $1,000$20.50 for the first $500 + $2.50 per additional $100 or fraction
$1,001 – $20,000$34.00 for the first $1,000 + $2.20 per additional $100 or fraction
$20,001 – $50,000$442.00 for the first $20,000 + $18.00 per additional $1,000 or fraction
$50,001 – $100,000$986.00 for the first $50,000 + $14.00 per additional $1,000 or fraction
$100,001 – $500,000$1,700.00 for the first $100,000 + $10.00 per additional $1,000 or fraction
$500,001 – $2,000,000$5,700.00 for the first $500,000 + $5.00 per additional $1,000 or fraction
Over $2,000,000$13,300.00 for the first $2,000,000 + $4.50 per additional $1,000 or fraction

What counts as project value

Not stated in the schedule. Plan review and permit fees 'are based on project value of work in each structure'; for multiple buildings the applicant gives the cost breakdown of each building and sitework. How the value is verified is in ROH 18-6, which could not be read.

Worked example: a $350,000 new home

  1. Building permit fee: $1,700.00 for the first $100,000.00 + $10.00 × 250 per $1,000.00 over = $4,200.00
  2. Plan review fee: 20% of $4,200.00 = $840.00
  3. Total before trade permits: $5,040.00.

Fees people miss

No other fees are listed in the schedule we captured.

How to apply

  1. Gather your plans and your project's total value.
  2. Submit to Department of Planning and Permitting.
  3. Pay the permit and plan review fees when invoiced.
  4. Questions: (808) 768-8000 · 650 South King Street, 7th Floor, Honolulu, HI 96813

How Honolulu compares

A $25,000 remodel costs $638.40 in Honolulu: 68% above the national median of $380.00.

A $75,000 addition costs $1,603.20 in Honolulu: about twice the national median of $820.58.

A $350,000 new home costs $5,040.00 in Honolulu: 73% above the national median of $2,918.63.

Same standard projects everywhere, including plan review and required surcharges. All Hawaii places · Compare side by side

Honolulu permit fee FAQ

How much is a building permit in Honolulu, HI?

A $25,000 remodel: $638.40. A $75,000 addition: $1,603.20. A $350,000 new single-family: $5,040.00. These include every fee the schedule applies to that project; trade permits are separate.

Is plan review included in the Honolulu permit fee?

No. Plan review is charged separately at 20% of the permit fee.

How does Honolulu determine project value?

Not stated in the schedule. Plan review and permit fees 'are based on project value of work in each structure'; for multiple buildings the applicant gives the cost breakdown of each building and sitework. How the value is verified is in ROH 18-6, which could not be read.

When did these Honolulu fees take effect?

The schedule does not state an effective date. We last checked it against the official source on Nov 4, 2026.